Permit Details

Status:
Final
Type:
COMMERCIAL ADDITION
Address:
5324 E 1ST ST
Address NEW:
5324 E 1ST ST
Apply Date:
10/30/2018
Applicant:
MAR DESIGNS PLC
Description:
4 NEW SITE RAMADAS
Architects:
  • RODRIGUEZ, MARIANO ANTONIO
Contractors:
  • SOUTHWEST REMODEL & REPAIR LLC

Permit Reviews

Permit Number - T18CM08684
Permit Status: Final
Permit Description: 4 NEW SITE RAMADAS
Start Date Submittal Complete Date Status  
10/30/2018 PLANS OK TO SUBMIT - COMM 11/01/2018 COMPLETED Review Details
11/01/2018 3RD PARTY REVIEW - COMMERCIAL 11/27/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM08684
Permit Status: Final
Permit Description: 4 NEW SITE RAMADAS
Total Outstanding Activity Conditions - 1
Date Name
10/30/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM08684
Permit Description: 4 NEW SITE RAMADAS
Total Completed Inspections - 15
Date Description Inspector Results Comments
11/28/2018 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved
12/03/2018 ELECTRIC - UNDERGROUND MRAMBER Approved 1st lift at columns ok
12/05/2018 ELECTRIC - INTERMEDIATE GWEST Approved Conduit and wire approved in columns for lighting and receptacles, etc.
12/05/2018 REINFORCED MASONRY PRE-GROUT GWEST Approved 10columns west and 4 columns east-this is final lift and OK for final grout pour.
12/12/2018 BUILDING PRE-SLAB RCHANDLER Approved
12/12/2018 ELECTRIC - OUTDOOR LIGHTING RCHANDLER Approved
12/18/2018 ROOF NAILING GWEST Approved No ladder to access
12/18/2018 EXT METAL CLIPS/EXT SHEATHING GWEST Approved No ladder to access
01/09/2019 ELECTRIC - ABOVE CEILING GWEST Approved approved upon 2090 approval from GWEST
01/09/2019 BUILDING ABOVE CEILING GWEST Approved approved upon 1090 approval from GWEST
01/09/2019 FRAMING GWEST Approved approved upon 1090 approval from GWEST
01/09/2019 STEM WALL/RETAINING WALL GWEST Approved approved upon 1090 approval from GWEST
01/09/2019 OUTDOOR LIGHTING FINAL GWEST Approved
01/09/2019 ELECTRIC - FINAL GWEST Approved
01/09/2019 BUILDING - FINAL GWEST Approved