Permit: T18CM08684
Permit Details
Apply Date:
10/30/2018
Applicant:
MAR DESIGNS PLC
Description:
4 NEW SITE RAMADAS
Architects:
- RODRIGUEZ, MARIANO ANTONIO
Contractors:
- SOUTHWEST REMODEL & REPAIR LLC
Permit Reviews
Permit Number - T18CM08684
Permit Status: Final
Permit Description: 4 NEW SITE RAMADAS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/30/2018 | PLANS OK TO SUBMIT - COMM | 11/01/2018 | COMPLETED |
| 11/01/2018 | 3RD PARTY REVIEW - COMMERCIAL | 11/27/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08684
Permit Status: Final
Permit Description: 4 NEW SITE RAMADAS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/30/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM08684
Permit Description: 4 NEW SITE RAMADAS
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
| 12/03/2018 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | 1st lift at columns ok |
| 12/05/2018 | ELECTRIC - INTERMEDIATE | GWEST | Approved | Conduit and wire approved in columns for lighting and receptacles, etc. |
| 12/05/2018 | REINFORCED MASONRY PRE-GROUT | GWEST | Approved | 10columns west and 4 columns east-this is final lift and OK for final grout pour. |
| 12/12/2018 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 12/12/2018 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
| 12/18/2018 | ROOF NAILING | GWEST | Approved | No ladder to access |
| 12/18/2018 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | No ladder to access |
| 01/09/2019 | ELECTRIC - ABOVE CEILING | GWEST | Approved | approved upon 2090 approval from GWEST |
| 01/09/2019 | BUILDING ABOVE CEILING | GWEST | Approved | approved upon 1090 approval from GWEST |
| 01/09/2019 | FRAMING | GWEST | Approved | approved upon 1090 approval from GWEST |
| 01/09/2019 | STEM WALL/RETAINING WALL | GWEST | Approved | approved upon 1090 approval from GWEST |
| 01/09/2019 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
| 01/09/2019 | ELECTRIC - FINAL | GWEST | Approved | |
| 01/09/2019 | BUILDING - FINAL | GWEST | Approved |