Permit: T18CM08511
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
6556 S BURCHAM AV
Address NEW:
6556 S BURCHAM AV
Apply Date:
10/24/2018
Applicant:
Description:
ADDITION: BEDROOM, KITCHEN, & BATHROOM
Permit Reviews
Permit Number - T18CM08511
Permit Status: Expired
Permit Description: ADDITION: BEDROOM, KITCHEN, & BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/24/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08511
Permit Status: Expired
Permit Description: ADDITION: BEDROOM, KITCHEN, & BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/24/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T18CM08511
Permit Status: Expired
Permit Description: ADDITION: BEDROOM, KITCHEN, & BATHROOM
| Date | Description | Comments |
|---|---|---|
| 10/26/2018 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM08511
Permit Description: ADDITION: BEDROOM, KITCHEN, & BATHROOM
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/17/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 01/23/2019 | COT - RSBU - Preslab | Passed | {Activity date: 01/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 01/23/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 01/30/2019 | COT - RSPL - Yard Water Line | Passed | {Activity date: 01/30/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 01/30/2019 | COT - RSPL - Sewer | Passed | {Activity date: 01/30/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 01/30/2019 | COT - RSPL - Backwater Valve | Passed | {Activity date: 01/30/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 04/02/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 04/02/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 04/02/2019 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 04/02/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 04/18/2019 | COT - LCBU - Framing | Passed | {Activity date: 04/18/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by CBELL1 - } ; {Activity date: 04/02/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by CBELL1 - Schedule Inspection when all Intermediates are complete. } |
|
| 04/18/2019 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 04/18/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by CBELL1 - } ; {Activity date: 01/30/2019; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } ; {Activity date: 01/29/2019; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 01/17/2019; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 04/18/2019 | RSEL - Electrical Progress | Passed | {Activity date: 04/18/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by CBELL1 - } | |
| 04/18/2019 | RSME - Mechanical Progress | Passed | {Activity date: 04/18/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by CBELL1 - Ok to insulate} | |
| 04/18/2019 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 04/18/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by CBELL1 - } | |
| 06/06/2019 | COT - RSME - Mechanical Final | Passed | {Activity date: 06/06/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - } | |
| 06/06/2019 | COT - BULD - SWG Clearance | Passed | {Activity date: 06/06/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - } | |
| 11/08/2019 | COT - RSPL - Plumbing Final | Passed | {Activity date: 11/08/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 06/06/2019; Status: Not ready for Inspection; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - too much work incomplete to inspect at this time. OK to clear gas for reconnection} | |
| 11/08/2019 | COT - RSEL - Electrical Final | Passed | {Activity date: 11/08/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 06/06/2019; Status: Not ready for Inspection; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - too much work incomplete to inspect at this time.} | |
| 11/12/2019 | RSBU - Building Final | Passed | {Activity date: 11/12/2019; Status: Approved; Inspector: KEN; Comment: Entered by KKARSEN1 - STUSS APPROVED} ; {Activity date: 11/08/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - APPROVED BY INSPECTOR, PENDING ROOF TRUSS APPROVAL} ; {Activity date: 06/06/2019; Status: Not ready for Inspection; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - too much work incomplete to inspect at this time.} |