Apply Date:
10/10/2018
Applicant:
FAHR, GREGORY A
Description:
SFR PLAN2105 T18-M0005
Architects:
- FAHR, GREGORY A
Permit Reviews
Permit Number - T18CM08122
Permit Status: Final
Permit Description: SFR PLAN2105 T18-M0005
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/10/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/12/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08122
Permit Status: Final
Permit Description: SFR PLAN2105 T18-M0005
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/10/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM08122
Permit Description: SFR PLAN2105 T18-M0005
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | make sure plumber is using correct glue at PVC ABS connection point. |
| 10/24/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
| 11/07/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | double check for leaks as meter was not turned on. |
| 11/07/2018 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 11/07/2018 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 11/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 02/07/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 02/07/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 02/28/2019 | TEP CLEARANCE - PM | GWEST | Approved | CODE ECO |
| 02/28/2019 | PLUMBING - GAS PRESSURE TEST | GWEST | Approved | |
| 02/28/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | |
| 02/28/2019 | ELECTRIC - CONSTRUCTION POWER | GWEST | Approved | |
| 02/28/2019 | FRAMING | GWEST | Approved | |
| 03/05/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
| 03/05/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
| 03/19/2019 | SHEET ROCK NAILING | GWEST | Approved | |
| 05/29/2019 | GAS CLEARANCE | MRAMBER | Approved | |
| 05/29/2019 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 05/29/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
| 05/29/2019 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 05/29/2019 | ELECTRIC - FINAL | MRAMBER | Approved | Gas connect OK to clear. Gas clearance provided toSWG. |
| 05/29/2019 | BUILDING - FINAL | MRAMBER | Approved | Gas connect OK to clear. Gas clearance provided toSWG. |