Permit: T18CM08031
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
5240 E KNIGHT DR #122
Address NEW:
5240 E KNIGHT DR #122
Apply Date:
10/09/2018
Applicant:
SWAN WAYNE E
Description:
OFFICE
Contractors:
- ROBERT CAYLOR CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T18CM08031
Permit Status: C of o
Permit Description: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/09/2018 | COMMERCIAL - TI | 10/24/2018 | COMPLETED |
| 10/24/2018 | RESUBMITTAL | 10/24/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08031
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/09/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08031
Permit Description: OFFICE
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2018 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ok to backfill |
| 11/05/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 11/05/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 11/05/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 11/05/2018 | FRAMING | DQUINN | Approved | |
| 11/21/2018 | MECHANICAL - ABOVE CEILING | GWEST | Approved | |
| 11/21/2018 | PLUMBING - ABOVE CEILING | GWEST | Approved | |
| 11/21/2018 | ELECTRIC - ABOVE CEILING | GWEST | Approved | |
| 11/21/2018 | BUILDING ABOVE CEILING | GWEST | Approved | |
| 12/21/2018 | FIRE - FINAL | jvincent | Approved | will mount extinguisher |
| 12/21/2018 | FIRE - ALARM FINAL | jvincent | Approved | no alarm |
| 12/21/2018 | MECHANICAL - FINAL | GWEST | Approved | |
| 12/21/2018 | PLUMBING - PROGRESS | GWEST | Approved | |
| 12/21/2018 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | |
| 12/21/2018 | ELECTRIC - FINAL | GWEST | Approved | |
| 12/21/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | No work outside building on approve plans |
| 12/27/2018 | BUILDING - FINAL | BJONES | Approved | |
| 12/27/2018 | PLUMBING - FINAL | BJONES | Approved |