Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM07914
Permit Details
Apply Date:
10/04/2018
Applicant:
MERITAGE HOMES CONSTRUCTION INC *** APA***
Description:
SFR plan130.1460 T18-M0012
Contractors:
- MERITAGE HOMES CONSTRUCTION INC *** APA***
Permit Reviews
Permit Number - T18CM07914
Permit Status: Final
Permit Description: SFR plan130.1460 T18-M0012
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/04/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07914
Permit Status: Final
Permit Description: SFR plan130.1460 T18-M0012
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/04/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM07914
Permit Description: SFR plan130.1460 T18-M0012
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/29/2018 | PLUMBING - SEWER HCS CONNECT | BJONES | Approved | |
10/29/2018 | PLUMBING - YARD WTR LINE/TEST | BJONES | Approved | |
10/29/2018 | PLUMBING - ROUGH, SOIL | BJONES | Approved | |
11/09/2018 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
11/09/2018 | ELECTRIC - UFER | TVALENCIA | Approved | 1- 20 feet of horizontal steel ufer provided. |
11/09/2018 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
11/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
11/27/2018 | ROOF NAILING | MHASSAN | Approved | |
11/27/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
12/31/2018 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
12/31/2018 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | |
12/31/2018 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
12/31/2018 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
12/31/2018 | FRAMING | DMUNIZ | Approved | |
01/10/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | CLEAR ECO |
01/10/2019 | SHEET ROCK NAILING | DMUNIZ | Approved | |
01/11/2019 | TEP CLEARANCE - AM | DMUNIZ | Approved | ECO |
03/06/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
03/13/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
03/13/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
03/13/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
03/13/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
03/13/2019 | BUILDING - FINAL | DMUNIZ | Approved |