Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM07786
Permit Details
Apply Date:
10/02/2018
Applicant:
CHRISTA PARSONS
Description:
DOG BAKERY
Architects:
- BRIGHT, RICK LANE
Contractors:
- AWARD INSTALLATIONS INC
Permit Reviews
Permit Number - T18CM07786
Permit Status: C of o
Permit Description: DOG BAKERY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/02/2018 | COMMERCIAL - TI | 10/02/2018 | COMPLETED |
10/03/2018 | REVISION - - 1ST | 10/03/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM07786
Permit Status: C of o
Permit Description: DOG BAKERY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM07786
Permit Description: DOG BAKERY
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
10/19/2018 | PLUMBING - ABOVE CEILING | BJONES | Approved | Please call for final inspection 3090 |
10/19/2018 | PLUMBING - INTERMEDIATE | BJONES | Approved | Please call for final inspection 3090 |
11/05/2018 | CERTIFICATE OF OCCUPANCY | GWEST | Approved | |
11/05/2018 | BUILDING - FINAL | GWEST | Approved | |
11/05/2018 | FRAMING | GWEST | Approved | |
11/05/2018 | PLUMBING - PROGRESS | GWEST | Approved | |
11/05/2018 | PLUMBING - FINAL | GWEST | Approved | |
11/05/2018 | MECHANICAL - FINAL | GWEST | Approved | |
11/05/2018 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
11/05/2018 | ELECTRIC - FINAL | GWEST | Approved | |
11/05/2018 | ELECTRIC - ABOVE CEILING | GWEST | Approved | |
11/05/2018 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
11/05/2018 | HEALTH DEPT - FINAL 724-7908 | PRICILLA | Approved | |
11/05/2018 | MECHANICAL - FINAL | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | MECHANICAL - INTERMEDIATE | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | PLUMBING - PROGRESS | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | ELECTRIC - FINAL | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | ELECTRIC - ABOVE CEILING | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | ELECTRIC - INTERMEDIATE | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | BUILDING - FINAL | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | FRAMING | GWEST | Approved | These 8 line items are approved upon completion of all COT Requirements and other department approvals and sign-offs. |
11/05/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
11/05/2018 | FIRE - FINAL | jvincent | Approved | will mount extinguisher next to front door. |
11/05/2018 | FIRE SPKLR - FINAL | jvincent | Approved |