Permit: T18CM07720
Permit Details
Apply Date:
09/28/2018
Applicant:
THRUSH, STEFANIE
Description:
TI: RESTAURANT-MCDONALD'S
Architects:
- SEMLING, GARY M
Contractors:
- DAMITIO CONSTRUCTION INC ,
Permit Reviews
Permit Number - T18CM07720
Permit Status: L of c
Permit Description: TI: RESTAURANT-MCDONALD'S
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/13/2019 | REVISION - - 1ST | 02/13/2019 | COMPLETED |
09/28/2018 | PLANS OK TO SUBMIT - COMM | 09/28/2018 | COMPLETED |
09/28/2018 | COMMERCIAL - TI | 11/05/2018 | COMPLETED |
11/15/2018 | RESUBMITTAL | 02/13/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07720
Permit Status: L of c
Permit Description: TI: RESTAURANT-MCDONALD'S
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM07720
Permit Description: TI: RESTAURANT-MCDONALD'S
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/15/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
01/18/2019 | ELECTRIC - UNDERGROUND | BJONES | Approved | 4-2" Conduits 10-3/4" ' ' |
01/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | Footing inspection approved for signs and lights |
01/31/2019 | BUILDING - PROGRESS | BJONES | Approved | 24" X 15’ Light pole base with 8#5 rebar with #3 wraps at 12” OC Ground wire 35’ #4 Copper, 4 3/4” pvc conduits 4 3/4" X 42" Bolts |
02/15/2019 | EXT METAL CLIPS/EXT SHEATHING | BJONES | Approved | |
02/19/2019 | PLUMBING - ROUGH, SOIL | BJONES | Approved | ADA compliant Restrooms Installed |
02/20/2019 | FRAMING | DQUINN | Approved | |
02/21/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
02/21/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
02/21/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
02/27/2019 | BUILDING ABOVE CEILING | BJONES | Approved | |
04/26/2019 | FIRE - FINAL | gsereno1 | Approved | |
04/26/2019 | NPPO - FINAL | BBENEDON | Approved | |
04/26/2019 | SIGN - FINAL | BBENEDON | Approved | |
04/26/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | |
04/26/2019 | STUCCO MESH | MRAMBER | Approved | |
04/26/2019 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
04/29/2019 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
04/29/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
04/29/2019 | ELECTRIC - PROGRESS | DQUINN | Approved | |
04/29/2019 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
06/17/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | PER STEVE SHIELDS. |
06/27/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
07/09/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
07/09/2019 | BUILDING - FINAL | DQUINN | Approved |