Permit: T18CM07663
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3289 E HEMISPHERE LP
Address NEW:
3289 E HEMISPHERE LP
Apply Date:
09/26/2018
Applicant:
ERIN HASTREITER
Description:
OFFICE/WAREHOUSE T.I
Architects:
- SWAN WAYNE E
Contractors:
- PATE CONTRACTORS LLC
Permit Reviews
Permit Number - T18CM07663
Permit Status: C of o
Permit Description: OFFICE/WAREHOUSE T.I
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2019 | REVISION - - 1ST | 01/30/2019 | COMPLETED |
| 09/26/2018 | COMMERCIAL - TI | 09/26/2018 | COMPLETED |
| 09/26/2018 | COMMERCIAL - TI | 11/26/2018 | COMPLETED |
| 11/26/2018 | COMMERCIAL - TI | 11/28/2018 | COMPLETED |
| 11/28/2018 | COMMERCIAL - TI | 12/03/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07663
Permit Status: C of o
Permit Description: OFFICE/WAREHOUSE T.I
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/26/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM07663
Permit Description: OFFICE/WAREHOUSE T.I
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 11/28/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 12/20/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | All electric and frame in storage and media closets, large conference room, warehouse and customer service are OK to one side and tape. Training rooms are not ready. |
| 12/20/2018 | FRAMING | DQUINN | Approved | All electric and frame in storage and media closets, large conference room, warehouse and customer service are OK to one side and tape. Training rooms are not ready. |
| 01/07/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
| 01/10/2019 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
| 01/10/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 02/20/2019 | ROOF NAILING | DQUINN | Approved | |
| 03/28/2019 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
| 03/28/2019 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
| 03/28/2019 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
| 03/28/2019 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
| 05/08/2019 | FIRE - ALARM FINAL | gsereno1 | Approved | Did not call in, but closed on alarms contractor final. |
| 05/13/2019 | FIRE - FINAL | MRoss | Approved | |
| 05/13/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 05/13/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 05/15/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 05/15/2019 | BUILDING - FINAL | DQUINN | Approved | |
| 05/15/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 05/15/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 05/15/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
| 05/15/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 05/16/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | APPROVED PER BUILDING FINAL |