Permit: T18CM07390
Permit Details
Apply Date:
09/18/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
HEATED SPRAY BOOTH
Contractors:
- RELY ON SPRAY BOOTH CO INC
Permit Reviews
Permit Number - T18CM07390
Permit Status: Expired
Permit Description: HEATED SPRAY BOOTH
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/18/2018 | COMMERCIAL - TI | 09/21/2018 | COMPLETED |
09/21/2018 | RESUBMITTAL | 09/21/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07390
Permit Status: Expired
Permit Description: HEATED SPRAY BOOTH
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/18/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM07390
Permite Description: HEATED SPRAY BOOTH
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
BUILDING - FINAL | N/A | Not Inspected | ||
MECHANICAL - INTERMEDIATE | N/A | Not Inspected | ||
09/18/2018 | MECHANICAL - FINAL | N/A | Prior to Final Inspectn | AIR BALANCE REPORT REQUIRED |
12/20/2018 | FIRE SPKLR - FINAL | N/A | Partial Approval | Need to confirm monitoring with John and Harvey |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM07390
Permit Description: HEATED SPRAY BOOTH
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | GWEST | Approved | 2 rebar mats for concrete pour |
12/18/2018 | PLUMBING - FINAL | DQUINN | Approved | |
12/18/2018 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
12/18/2018 | BUILDING - PROGRESS | DQUINN | Approved | |
12/18/2018 | BUILDING ABOVE CEILING | DQUINN | Approved | |
12/18/2018 | FRAMING | DQUINN | Approved | |
12/18/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
12/18/2018 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
12/18/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
12/20/2018 | FIRE - FINAL | JPEELDAVIS | Approved | Need placard for hazard on the paint booth Sticker Placard is NOT allowed. Need .003 mil plastic on the heads prior to completion |