Permit: T18CM07325
Permit Details
Apply Date:
09/14/2018
Applicant:
INTERIOR TRENDS REMODEL L L C
Description:
SFR REMODEL AND ADDITION
Contractors:
- INTERIOR TRENDS REMODEL L L C
Permit Reviews
Permit Number - T18CM07325
Permit Status: Expired
Permit Description: SFR REMODEL AND ADDITION
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/16/2019 | REVISION - - 1ST | 01/16/2019 | COMPLETED |
03/18/2019 | REVISION - - 2ND | 03/18/2019 | COMPLETED |
09/14/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 09/14/2018 | COMPLETED |
09/14/2018 | RESIDENTIAL - BLDG/WWM | 10/25/2018 | COMPLETED |
10/25/2018 | RESUBMITTAL | 10/31/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07325
Permit Status: Expired
Permit Description: SFR REMODEL AND ADDITION
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/14/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM07325
Permite Description: SFR REMODEL AND ADDITION
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
FIRE SPKLR - FINAL | N/A | Not Inspected |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM07325
Permit Description: SFR REMODEL AND ADDITION
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/04/2018 | ELECTRIC - CONSTRUCTION POWER | RCHANDLER | Approved | TEP-INCR |
12/05/2018 | TEP CLEARANCE - AM | RCHANDLER | Approved | INCR |
01/24/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
02/05/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
02/05/2019 | ELECTRIC - UFER | DQUINN | Approved | |
02/05/2019 | BUILDING PRE-SLAB | DQUINN | Approved | |
02/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
04/17/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | Based on 2/5/19 inspection results. |
04/17/2019 | ROOF NAILING | RCHANDLER | Approved | |
04/17/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
05/15/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE INCR |
05/15/2019 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | Clearance INCR. cutover for new service. |
06/18/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
06/18/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
06/18/2019 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | |
06/18/2019 | PLUMBING - GAS PRESSURE TEST | GWEST | Approved | |
06/18/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | |
06/18/2019 | FRAMING | GWEST | Approved | |
08/13/2019 | PLUMBING - FINAL | RCHANDLER | Approved | Observed shower liner test. |
03/26/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
03/26/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
03/26/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
03/26/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
03/26/2020 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | |
03/27/2020 | GAS CLEARANCE | DMUNIZ | Approved |