Permit: T18CM07103
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
915 N CAMINO MIRAMONTE
Address NEW:
915 N CAMINO MIRAMONTE
Apply Date:
09/10/2018
Applicant:
B T H CONSTRUCTION L L C ,
Description:
GUEST HOUSE
Contractors:
- B T H CONSTRUCTION L L C ,
Permit Reviews
Permit Number - T18CM07103
Permit Status: Final
Permit Description: GUEST HOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/10/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 09/10/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07103
Permit Status: Final
Permit Description: GUEST HOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/10/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM07103
Permit Description: GUEST HOUSE
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/05/2018 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 10/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 11/30/2018 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 12/05/2018 | ROOF NAILING | RCHANDLER | Approved | |
| 12/11/2018 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
| 12/11/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 12/14/2018 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | |
| 01/23/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 01/23/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 01/23/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 01/23/2019 | FRAMING | RCHANDLER | Approved | |
| 04/24/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 04/24/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 04/24/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 04/24/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 07/15/2019 | BUILDING - FINAL | CTREVIL | Approved | FINALS PENDING IMPACT FEE PAYMENT - CHANDLER COMPLETED LAST INSPECTION ON 4/24/19 |