Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM06870
Permit Details
Apply Date:
08/31/2018
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR 4816MODEL T18-M0034
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T18CM06870
Permit Status: Final
Permit Description: SFR 4816MODEL T18-M0034
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/31/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/31/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06870
Permit Status: Final
Permit Description: SFR 4816MODEL T18-M0034
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/31/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM06870
Permit Description: SFR 4816MODEL T18-M0034
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/05/2018 | PLUMBING - SEWER HCS CONNECT | GWest | Approved | |
10/05/2018 | PLUMBING - YARD WTR LINE/TEST | GWest | Approved | |
10/05/2018 | PLUMBING - ROUGH, SOIL | GWest | Approved | |
10/19/2018 | ELECTRIC - UFER | BJONES | Approved | |
10/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | |
11/01/2018 | PLUMBING - PRE SLAB | TVALENCIA | Approved | |
11/01/2018 | ELECTRIC - TEMPORARY SERVICE | TVALENCIA | Approved | 1- Clear electric ECO |
11/01/2018 | ELECTRIC - PROGRESS | TVALENCIA | Approved | |
11/01/2018 | ROOF NAILING | TVALENCIA | Approved | |
11/01/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
11/01/2018 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
11/02/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
11/29/2018 | PLUMBING - BACK WATER VALVE | MHASSAN | Approved | |
11/29/2018 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
11/29/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | |
11/29/2018 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
11/29/2018 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
11/29/2018 | U VALUE FOR WINDOW | MHASSAN | Approved | |
11/29/2018 | FRAMING | MHASSAN | Approved | finish nailing off FHA plates |
12/04/2018 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
12/14/2018 | SHEET ROCK NAILING | DMUNIZ | Approved | |
12/14/2018 | SHEET ROCK NAILING | MHASSAN | Approved | WALLS TEXTURED AT TIME OF INSPECTION |
01/04/2019 | PLUMBING - PROGRESS | DMUNIZ | Approved | GAS CLEARANCE ONLY. |
01/07/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
01/15/2019 | MECHANICAL - PROGRESS | DMUNIZ | Approved | approved upon 4090 approval from DMUNIZ |
01/15/2019 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | approved upon 4090 approval from DMUNIZ |
01/15/2019 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | approved upon 2090 approval from DMUNIZ |
01/15/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
01/15/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
01/16/2019 | SITE - SEWER | DMUNIZ | Approved | approved upon 3090 approval from DMUNIZ |
01/16/2019 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | approved upon 3090 approval from DMUNIZ |
01/16/2019 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | approved upon 3090 approval from DMUNIZ |
01/16/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
01/16/2019 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | approved upon 2090 approval from DMUNIZ |
01/16/2019 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | approved upon 2090 approval from DMUNIZ |
01/16/2019 | BUILDING ABOVE CEILING | DMUNIZ | Approved | approved upon 1090 approval from DMUNIZ |
01/16/2019 | BUILDING - PROGRESS | DMUNIZ | Approved | approved upon 1090 approval from DMUNIZ |
01/16/2019 | BUILDING - FINAL | DMUNIZ | Approved | |
01/16/2019 | PLUMBING - FINAL | DMUNIZ | Approved |