Permit: T18CM06810
Permit Details
Apply Date:
08/29/2018
Applicant:
N/A
Description:
ECO SITE - CELL TOWER
Contractors:
- ENERTECH RESOURCES LLC
Permit Reviews
Permit Number - T18CM06810
Permit Status: L of c
Permit Description: ECO SITE - CELL TOWER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2018 | CELL TOWER/ANTENNAS | 08/30/2018 | COMPLETED |
| 08/30/2018 | CELL TOWER/ANTENNAS | 09/19/2018 | COMPLETED |
| 09/19/2018 | CELL TOWER/ANTENNAS | 10/15/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM06810
Permit Status: L of c
Permit Description: ECO SITE - CELL TOWER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/29/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM06810
Permit Description: ECO SITE - CELL TOWER
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 12/26/2018 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | |
| 04/08/2019 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | ECO |
| 04/08/2019 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | |
| 04/08/2019 | FRAMING | RCAMACHO | Approved | |
| 04/08/2019 | ELECTRIC - UFER | RCAMACHO | Approved | |
| 06/27/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | approval is only for area within CMU walls. |
| 08/07/2019 | TEP CLEARANCE - PM | RCAMACHO | Approved | CODE RECN |
| 09/27/2019 | BUILDING - FINAL | DMUNIZ | Approved | SUBMIT SPECIAL INSPECTION REPORTS PRIOR TO FINAL |
| 09/27/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 09/27/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved |