Permit: T18CM06804
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
2851 N FLOWING WELLS RD 121
Address NEW:
2851 N FLOWING WELLS RD 121
Apply Date:
08/29/2018
Applicant:
CDG ARCHITECTS -CINDY HOGAN-
Description:
TI: WAREHOUSE
Architects:
- CDG ARCHITECTS
Permit Reviews
Permit Number - T18CM06804
Permit Status: C of o
Permit Description: TI: WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2018 | COMMERCIAL - TI | 09/06/2018 | COMPLETED |
| 09/06/2018 | COMMERCIAL - TI | 09/10/2018 | COMPLETED |
| 09/10/2018 | COMMERCIAL - TI | 09/11/2018 | COMPLETED |
| 09/11/2018 | COMMERCIAL - TI | 09/11/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06804
Permit Status: C of o
Permit Description: TI: WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/29/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM06804
Permit Description: TI: WAREHOUSE
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2018 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 09/24/2018 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 09/24/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 09/24/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
| 09/24/2018 | FRAMING | ESTEVENS | Approved | |
| 10/03/2018 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | The TEP code is INCR |
| 10/04/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 10/05/2018 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
| 10/05/2018 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 10/08/2018 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 10/23/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 10/23/2018 | FIRE - FINAL | CBASALDUA | Approved | |
| 10/23/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 10/24/2018 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 10/25/2018 | BUILDING - FINAL | RSHERRY | Approved | |
| 10/25/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
| 10/25/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |