Permit: T18CM05874
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
9834 E FOREST GROVE LP
Address NEW:
9834 E FOREST GROVE LP
Apply Date:
07/30/2018
Applicant:
Description:
NEW SFR
Permit Reviews
Permit Number - T18CM05874
Permit Status: Expired
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/30/2018 | PLANS OK TO SUBMIT - RES | 07/30/2018 | COMPLETED |
| 07/30/2018 | RESIDENTIAL - BLDG/WWM | 03/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05874
Permit Status: Expired
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/30/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 08/01/2018 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM05874
Permit Description: NEW SFR
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2018 | COT - RSBU - Stem Wall/Retaining Wall | Passed | {Activity date: 08/10/2018; Status: Approved; Inspector: dflores2; Comment: Entered by DFLORES2 - OK TO GROUT STEM WALL UP TO WHERE INSPECTION WAS DONE} | |
| 08/16/2018 | COT - RSBU - Masonry Pregrout | Passed | {Activity date: 08/16/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - } | |
| 10/02/2018 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/02/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CMURPHY1 - this approval is for the second floor Underground} ; {Activity date: 09/04/2018; Status: Approved; Inspector: DFLORES2; Comment: Entered by DFLORES2 - IVRS - Inspection :*} | |
| 10/05/2018 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/05/2018; Status: Approved; Inspector: BJONES; Comment: Entered by BJONES1 - 20' #4 UFER IN SE CORNER} | |
| 10/05/2018 | COT - RSBU - Preslab | Passed | {Activity date: 10/05/2018; Status: Approved; Inspector: BJONES; Comment: Entered by BJONES1 - #3 REBAR IN SLAB, NOT SHOWN ON PLANS} ; {Activity date: 09/11/2018; Status: Partial Approval; Inspector: DFLORES; Comment: Entered by CMURPHY1 - } | |
| 10/05/2018 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/05/2018; Status: Approved; Inspector: BJONES; Comment: Entered by BJONES1 - #3 REBAR IN SLAB, NOT SHOWN ON PLANS} ; {Activity date: 09/11/2018; Status: Partial Approval; Inspector: DFLORES; Comment: Entered by CMURPHY1 - BASEMENT POUR IS OK TO PROCEED} ; {Activity date: 08/06/2018; Status: Partial Approval; Inspector: DFLORES2; Comment: Entered by DFLORES2 - BASEMENT RETAINING WALL OK TO POUR FOOTER} | |
| 10/26/2018 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/26/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } ; {Activity date: 10/19/2018; Status: Correction Required; Inspector: GWEST; Comment: Entered by CBELL1 - No plans or people on site} ; {Activity date: 08/01/2018; Status: Prior to Intermediates; Inspector: KEN; Comment: Entered by KKARSEN1 - ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION} | |
| 11/07/2018 | COT - RSME - Mechanical Final | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 11/07/2018 | COT - LCBU - Framing | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 11/07/2018 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } ; {Activity date: 10/02/2018; Status: Not ready for Inspection; Inspector: MHASSAN; Comment: Entered by CMURPHY1 - } | |
| 11/07/2018 | COT - RSPL - Yard Water Line | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 11/07/2018 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 11/07/2018 | RSEL - Electrical Progress | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 11/07/2018 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 11/07/2018; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - } | |
| 12/21/2018 | COT - RSEL - Electrical Underground | Passed | {Activity date: 12/21/2018; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - } | |
| 12/21/2018 | COT - RSEL - Construction Power | Passed | {Activity date: 12/21/2018; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - TEP ECO Construction Power located in garage} |
|
| 12/21/2018 | BULD - Electrical Clearance | Passed | {Activity date: 12/21/2018; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - ECO} | |
| 02/01/2019 | COT - RSPL - Sewer | Passed | {Activity date: 02/01/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by CBELL1 - } | |
| 02/20/2019 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 02/20/2019; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - } | |
| 02/27/2019 | COT - RSPL - Plumbing Final | Passed | {Activity date: 02/27/2019; Status: Approved; Inspector: GWEST; Comment: Entered by CBELL1 - SW Gas Clearance Approved New Connect} ; {Activity date: 02/20/2019; Status: Not ready for Inspection; Inspector: BJONES; Comment: Entered by CBELL1 - Work incomplete} |
|
| 02/27/2019 | COT - BULD - SWG Clearance | Passed | {Activity date: 02/27/2019; Status: Approved; Inspector: GWEST; Comment: Entered by CBELL1 - } | |
| 03/01/2019 | RSBU - Building Final | Passed | {Activity date: 03/01/2019; Status: Approved; Inspector: GWEST; Comment: Entered by VFLORES1 - } ; {Activity date: 02/27/2019; Status: Correction Required; Inspector: GWEST; Comment: Entered by CBELL1 - Permanent address required on house. Caulk in AC disconnects on top and sides Install second story balcony guardrail at back deck} |
|
| 03/01/2019 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/01/2019; Status: Approved; Inspector: GWEST; Comment: Entered by VFLORES1 - } ; {Activity date: 02/27/2019; Status: Correction Required; Inspector: GWEST; Comment: Entered by CBELL1 - Secure electrical AC whip to wall to protect and get it off the ground} ; {Activity date: 02/20/2019; Status: Not ready for Inspection; Inspector: BJONES; Comment: Entered by CBELL1 - Work incomplete} | |
| 03/25/2019 | RSME - Mechanical Progress | Passed | {Activity date: 03/25/2019; Status: Approved; Inspector: GWEST; Comment: Entered by QJONES1 - APPROVED PER BUILDING FINAL} ; {Activity date: 02/20/2019; Status: Not ready for Inspection; Inspector: BJONES; Comment: Entered by CBELL1 - Work incomplete} |