Permit: T18CM05806
Permit Details
Apply Date:
07/26/2018
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR 4822MODEL T18-M0035
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T18CM05806
Permit Status: Final
Permit Description: SFR 4822MODEL T18-M0035
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/26/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05806
Permit Status: Final
Permit Description: SFR 4822MODEL T18-M0035
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/26/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM05806
Permit Description: SFR 4822MODEL T18-M0035
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/10/2018 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | IVRS - Inspection :* |
08/10/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
08/23/2018 | PLUMBING - YARD WTR LINE/TEST | MRAMBER1 | Approved | IVRS - Inspection :* |
08/23/2018 | PLUMBING - PRE SLAB | MRAMBER1 | Approved | IVRS - Inspection :* |
08/23/2018 | ELECTRIC - TEMPORARY SERVICE | MRAMBER1 | Approved | IVRS - Inspection :* |
08/23/2018 | ELECTRIC - UFER | MRAMBER1 | Approved | IVRS - Inspection :* |
08/23/2018 | BUILDING PRE-SLAB | MRAMBER1 | Approved | IVRS - Inspection :* |
08/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER1 | Approved | IVRS - Inspection :* |
08/24/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
09/11/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
09/12/2018 | ROOF NAILING | MRAMBER1 | Approved | IVRS - Inspection :* |
09/26/2018 | MECHANICAL - INTERMEDIATE | GWest | Approved | |
09/26/2018 | U VALUE FOR WINDOW | GWest | Approved | |
09/26/2018 | STUCCO MESH | GWest | Approved | |
09/26/2018 | FRAMING | GWest | Approved | |
10/01/2018 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | IVRS - Inspection :* |
10/01/2018 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
10/01/2018 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
10/10/2018 | SHEET ROCK NAILING | BJONES1 | Approved | No Sheer |
11/06/2018 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | SWG |
11/06/2018 | PLUMBING - PROGRESS | RCHANDLER | Approved | |
11/07/2018 | GAS CLEARANCE | RCHANDLER | Approved | |
11/13/2018 | MECHANICAL - PROGRESS | GWEST | Approved | |
11/13/2018 | MECHANICAL - ABOVE CEILING | GWEST | Approved | |
11/13/2018 | SITE - SEWER | GWEST | Approved | |
11/13/2018 | PLUMBING - BACK WATER VALVE | GWEST | Approved | |
11/13/2018 | PLUMBING - ABOVE CEILING | GWEST | Approved | |
11/13/2018 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
11/13/2018 | ELECTRIC - PROGRESS | GWEST | Approved | |
11/13/2018 | ELECTRIC - ABOVE CEILING | GWEST | Approved | |
11/13/2018 | BUILDING - PROGRESS | GWEST | Approved | |
11/13/2018 | BUILDING ABOVE CEILING | GWEST | Approved | |
11/13/2018 | ELECTRIC - SERVICE UPGRADE | GWEST | Approved | |
11/13/2018 | ELECTRIC - FINAL | GWEST | Approved | |
11/13/2018 | MECHANICAL - FINAL | GWEST | Approved | |
11/13/2018 | PLUMBING - FINAL | GWEST | Approved | |
11/13/2018 | ELECTRIC - OUTDOOR LIGHTING | GWEST | Approved | |
11/13/2018 | BUILDING - FINAL | GWEST | Approved |