Permit: T18CM05740
Permit Details
Apply Date:
07/24/2018
Applicant:
N/A
Description:
ELECTRONIC - INSTALL COMM. PV SYSTEM AND RELATED MATERIALS
Contractors:
- URBAN ENERGY SOLUTIONS INC ***APA***
Permit Reviews
Permit Number - T18CM05740
Permit Status: L of c
Permit Description: ELECTRONIC - INSTALL COMM. PV SYSTEM AND RELATED MATERIALS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/24/2018 | WALK THRU - COMM | 08/17/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05740
Permit Status: L of c
Permit Description: ELECTRONIC - INSTALL COMM. PV SYSTEM AND RELATED MATERIALS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/24/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM05740
Permit Description: ELECTRONIC - INSTALL COMM. PV SYSTEM AND RELATED MATERIALS
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2018 | ELECTRIC - UFER | TVALENCIA | Approved | 1- Ufer ground conductor provided on columns and okay for concrete. |
| 12/13/2018 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 12/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 02/21/2019 | ELECTRIC - PROGRESS | TVALENCIA | Approved | Clear electric INCR |
| 03/12/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE DGC |
| 03/12/2019 | ELECTRIC - FINAL | MHASSAN | Approved | OK to clear solar DGC |
| 03/12/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 03/12/2019 | BUILDING - FINAL | MHASSAN | Approved | |
| 03/12/2019 | FRAMING | MHASSAN | Approved | |
| 03/12/2019 | ROOF NAILING | MHASSAN | Approved |