Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
2001 E GANLEY RD
Address NEW:
2001 E GANLEY RD
Apply Date:
07/18/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: INDUSTRIAL
Architects:
  • MICKELBERG, PAUL DAVID
Contractors:
  • DIVISION II CONSTRUCTION COMPANY

Permit Reviews

Permit Number - T18CM05595
Permit Status: L of c
Permit Description: TI: INDUSTRIAL
Start Date Submittal Complete Date Status  
07/18/2018 PLANS OK TO SUBMIT - COMM 07/18/2018 COMPLETED Review Details
07/20/2018 3RD PARTY REVIEW - COMMERCIAL TI 09/06/2018 COMPLETED Review Details
09/06/2018 POST 3RD PARTY REVIEW 09/13/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM05595
Permit Status: L of c
Permit Description: TI: INDUSTRIAL
Total Outstanding Activity Conditions - 1
Date Name
07/18/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T18CM05595
Permit Description: TI: INDUSTRIAL
Total Completed Inspections - 24
Date Description Inspector Results Comments
10/10/2018 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved
11/13/2018 BUILDING PRE-SLAB MRAMBER Approved
11/19/2018 PLUMBING - PRE SLAB GWEST Approved Bath and outer room area under test!
02/14/2019 MECHANICAL - INTERMEDIATE RCAMACHO Approved
02/14/2019 ELECTRIC - INTERMEDIATE RCAMACHO Approved
03/01/2019 SHEET ROCK NAILING RCAMACHO Approved
04/08/2019 PLUMBING - ABOVE CEILING RCAMACHO Approved
04/08/2019 ELECTRIC - ABOVE CEILING RCAMACHO Approved
04/11/2019 MECHANICAL - ABOVE CEILING AKLEINSORGE Approved
04/11/2019 PLUMBING - INTERMEDIATE AKLEINSORGE Approved
04/11/2019 PLUMBING - ROUGH, SOIL AKLEINSORGE Approved
04/11/2019 BUILDING ABOVE CEILING AKLEINSORGE Approved
04/11/2019 FRAMING AKLEINSORGE Approved
05/06/2019 FIRE SPKLR - FINAL MRoss Approved
05/13/2019 ELECTRIC - FINAL AKLEINSORGE Approved
05/13/2019 NPPO - FINAL BBENEDON Approved
05/13/2019 SIGN - FINAL BBENEDON Approved
05/13/2019 LANDSCAPE - FINAL BBENEDON Approved
05/14/2019 ENGINEERING - FINAL BBENEDON Approved
05/14/2019 RIGHT OF WAY - FINAL Bravin Approved
05/23/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER STERILIZATION REPORT COMPLETED
05/23/2019 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
06/07/2019 FIRE - FINAL gsereno1 Approved
06/11/2019 BUILDING - FINAL CTREVIL Approved