Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
07/12/2018
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR 4818MODEL T18-M0032
Contractors:
  • D R H TUCSON CONSTRUCTION

Permit Reviews

Permit Number - T18CM05465
Permit Status: Final
Permit Description: SFR 4818MODEL T18-M0032
Start Date Submittal Complete Date Status  
07/12/2018 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 07/12/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM05465
Permit Status: Final
Permit Description: SFR 4818MODEL T18-M0032
Total Outstanding Activity Conditions - 1
Date Name
07/12/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM05465
Permit Description: SFR 4818MODEL T18-M0032
Total Completed Inspections - 37
Date Description Inspector Results Comments
07/18/2018 PLUMBING - SEWER HCS CONNECT MHASSAN1 Approved
07/18/2018 PLUMBING - ROUGH, SOIL MHASSAN1 Approved FIX LEAK AT CLEANOUTS
07/20/2018 ELECTRIC - TEMPORARY SERVICE GWest Approved TEP-ECO
07/20/2018 ELECTRIC - UFER GWest Approved
07/20/2018 BUILDING PRE-SLAB GWest Approved
07/20/2018 EXCAVATION/LAYOUT REBAR & ZON GWest Approved
07/23/2018 TEP CLEARANCE - AM GWEST Approved ECO
07/25/2018 PLUMBING - PRE SLAB GWest Approved Super is Paul. Plumbing pre-slab already done
07/25/2018 ROOF NAILING GWest Approved
07/25/2018 EXT METAL CLIPS/EXT SHEATHING GWest Approved
07/27/2018 PLUMBING - GAS PRESSURE TEST mramber1 Approved
07/30/2018 MECHANICAL - INTERMEDIATE MHASSAN1 Approved IVRS - Inspection :* FIX AND SECURE DRYER VENT, CONNECTION NOT SECURE INSIDE OF WALL.
07/30/2018 PLUMBING - INTERMEDIATE MHASSAN1 Approved IVRS - Inspection :* DOMESTIC WATER LINES NOT HOLDING PRESSURE, THEY NEED TO BE CHECKED FOR LEAKS.
07/30/2018 FRAMING MHASSAN1 Approved IVRS - Inspection :* 1. CHECK MIDDLE BEARING WALL, NEEDS TO BE SHIMMED. 2. ADD TRIMMER STUD AT OPENING INTO SALES OFFICE. 3. FINISH NAILING PLATES.
07/30/2018 ELECTRIC - INTERMEDIATE MHASSAN1 Approved IVRS - Inspection :*
07/31/2018 U VALUE FOR WINDOW MHASSAN1 Approved
07/31/2018 FIREWALL/FIREBARRIER/FIRESTOP MHASSAN1 Approved
07/31/2018 MECHANICAL - PROGRESS MHASSAN1 Approved
07/31/2018 MECHANICAL - ABOVE CEILING MHASSAN1 Approved
07/31/2018 PLUMBING - ABOVE CEILING MHASSAN1 Approved
07/31/2018 ELECTRIC - ABOVE CEILING MHASSAN1 Approved
07/31/2018 BUILDING - PROGRESS MHASSAN1 Approved
07/31/2018 STUCCO MESH MHASSAN1 Approved
08/01/2018 SHEET ROCK NAILING GWest Approved
08/07/2018 PLUMBING - YARD WTR LINE/TEST TVALENC1 Approved IVRS - Inspection :*
08/14/2018 MECHANICAL - FINAL GWest Approved
08/15/2018 PLUMBING - PROGRESS TVALENC1 Approved
08/15/2018 ELECTRIC - PROGRESS TVALENC1 Approved
08/15/2018 PLUMBING - FINAL TVALENC1 Approved IVRS - Inspection :*
08/15/2018 PLUMBING - GAS PRESS TEST FNL TVALENC1 Approved IVRS - Inspection :*
08/15/2018 OUTDOOR LIGHTING FINAL TVALENC1 Approved IVRS - Inspection :*
08/15/2018 ELECTRIC - OUTDOOR LIGHTING TVALENC1 Approved IVRS - Inspection :*
08/15/2018 ELECTRIC - SERVICE UPGRADE TVALENC1 Approved IVRS - Inspection :*
08/15/2018 BUILDING - FINAL TVALENC1 Approved IVRS - Inspection :*
08/15/2018 BUILDING ABOVE CEILING TVALENC1 Approved IVRS - Inspection :*
08/20/2018 ELECTRIC - FINAL TVALENCIA Approved
01/30/2019 GAS CLEARANCE AQUIROZ Approved