Permit: T18CM05465
Permit Details
Apply Date:
07/12/2018
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR 4818MODEL T18-M0032
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T18CM05465
Permit Status: Final
Permit Description: SFR 4818MODEL T18-M0032
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/12/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/12/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05465
Permit Status: Final
Permit Description: SFR 4818MODEL T18-M0032
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM05465
Permit Description: SFR 4818MODEL T18-M0032
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
07/18/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | FIX LEAK AT CLEANOUTS |
07/20/2018 | ELECTRIC - TEMPORARY SERVICE | GWest | Approved | TEP-ECO |
07/20/2018 | ELECTRIC - UFER | GWest | Approved | |
07/20/2018 | BUILDING PRE-SLAB | GWest | Approved | |
07/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | GWest | Approved | |
07/23/2018 | TEP CLEARANCE - AM | GWEST | Approved | ECO |
07/25/2018 | PLUMBING - PRE SLAB | GWest | Approved | Super is Paul. Plumbing pre-slab already done |
07/25/2018 | ROOF NAILING | GWest | Approved | |
07/25/2018 | EXT METAL CLIPS/EXT SHEATHING | GWest | Approved | |
07/27/2018 | PLUMBING - GAS PRESSURE TEST | mramber1 | Approved | |
07/30/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | IVRS - Inspection :* FIX AND SECURE DRYER VENT, CONNECTION NOT SECURE INSIDE OF WALL. |
07/30/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | IVRS - Inspection :* DOMESTIC WATER LINES NOT HOLDING PRESSURE, THEY NEED TO BE CHECKED FOR LEAKS. |
07/30/2018 | FRAMING | MHASSAN1 | Approved | IVRS - Inspection :* 1. CHECK MIDDLE BEARING WALL, NEEDS TO BE SHIMMED. 2. ADD TRIMMER STUD AT OPENING INTO SALES OFFICE. 3. FINISH NAILING PLATES. |
07/30/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | IVRS - Inspection :* |
07/31/2018 | U VALUE FOR WINDOW | MHASSAN1 | Approved | |
07/31/2018 | FIREWALL/FIREBARRIER/FIRESTOP | MHASSAN1 | Approved | |
07/31/2018 | MECHANICAL - PROGRESS | MHASSAN1 | Approved | |
07/31/2018 | MECHANICAL - ABOVE CEILING | MHASSAN1 | Approved | |
07/31/2018 | PLUMBING - ABOVE CEILING | MHASSAN1 | Approved | |
07/31/2018 | ELECTRIC - ABOVE CEILING | MHASSAN1 | Approved | |
07/31/2018 | BUILDING - PROGRESS | MHASSAN1 | Approved | |
07/31/2018 | STUCCO MESH | MHASSAN1 | Approved | |
08/01/2018 | SHEET ROCK NAILING | GWest | Approved | |
08/07/2018 | PLUMBING - YARD WTR LINE/TEST | TVALENC1 | Approved | IVRS - Inspection :* |
08/14/2018 | MECHANICAL - FINAL | GWest | Approved | |
08/15/2018 | PLUMBING - PROGRESS | TVALENC1 | Approved | |
08/15/2018 | ELECTRIC - PROGRESS | TVALENC1 | Approved | |
08/15/2018 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | PLUMBING - GAS PRESS TEST FNL | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | ELECTRIC - SERVICE UPGRADE | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
08/15/2018 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
08/20/2018 | ELECTRIC - FINAL | TVALENCIA | Approved | |
01/30/2019 | GAS CLEARANCE | AQUIROZ | Approved |