Permit: T18CM05312
Permit Details
Apply Date:
07/09/2018
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C
Description:
SFR PEPP0030 T15-M0010
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T18CM05312
Permit Status: C of o
Permit Description: SFR PEPP0030 T15-M0010
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/09/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/10/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05312
Permit Status: C of o
Permit Description: SFR PEPP0030 T15-M0010
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/09/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05312
Permit Description: SFR PEPP0030 T15-M0010
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/24/2018 | PLUMBING - SEWER HCS CONNECT | DFLORES2 | Approved | |
| 07/24/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | |
| 08/02/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED |
| 08/02/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 08/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 09/21/2018 | ROOF NAILING | BJONES | Approved | |
| 09/21/2018 | EXT METAL CLIPS/EXT SHEATHING | BJONES | Approved | |
| 10/05/2018 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
| 10/05/2018 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 10/08/2018 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 10/09/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | |
| 10/23/2018 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 10/23/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | |
| 10/23/2018 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 10/23/2018 | U VALUE FOR WINDOW | MHASSAN | Approved | |
| 10/23/2018 | STUCCO MESH | MHASSAN | Approved | |
| 11/06/2018 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/06/2018 | FRAMING | DMCCARTHY | Approved | |
| 11/16/2018 | SHEET ROCK NAILING | TVALENCIA | Approved | |
| 02/04/2019 | MECHANICAL - FINAL | MHASSAN | Approved | |
| 02/04/2019 | PLUMBING - FINAL | MHASSAN | Approved | |
| 02/04/2019 | PLUMBING - GAS PRESS TEST FNL | MHASSAN | Approved | OK to clear gas for new service |
| 02/04/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | fix Canlite at front entr |
| 02/04/2019 | ELECTRIC - FINAL | MHASSAN | Approved | fix GFCI circuit |
| 02/05/2019 | GAS CLEARANCE | MHASSAN | Approved | |
| 02/06/2019 | BUILDING - PROGRESS | TVALENCIA | Approved | |
| 02/06/2019 | BUILDING - FINAL | TVALENCIA | Approved |