Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM05262
Permit Details
Apply Date:
07/06/2018
Applicant:
N/A
Description:
RESTAURANT
Architects:
- ANDREWS, DONALD A JR
Contractors:
- MC MANUS CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM05262
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/06/2018 | PLANS OK TO SUBMIT - COMM | 07/11/2018 | COMPLETED |
07/11/2018 | COMMERCIAL - NEW | 09/14/2018 | COMPLETED |
09/14/2018 | COMMERCIAL - NEW | 10/23/2018 | COMPLETED |
10/23/2018 | RESUBMITTAL | 10/25/2018 | COMPLETED |
10/25/2018 | RESUBMITTAL | 10/26/2018 | COMPLETED |
10/26/2018 | RESUBMITTAL | 10/26/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM05262
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/06/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05262
Permit Description: RESTAURANT
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
10/25/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT REQUIRED |
11/01/2018 | ELECTRIC - UFER | TVALENCIA | Approved | 1- 20 feet of horizontal steel ufer provided. |
11/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
11/06/2018 | STEM WALL/RETAINING WALL | TVALENCIA | Approved | |
11/19/2018 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
11/30/2018 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
12/04/2018 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ok to backfill 2" pvc from building to meter. |
12/14/2018 | PLUMBING - INTERMEDIATE | BJONES | Approved | Tank only |
12/17/2018 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
12/28/2018 | ELECTRIC - UNDERGROUND | DQUINN | Approved | S,E,N underground conduits ok to backfill. |
01/07/2019 | FRAMING | BJONES | Approved | |
01/07/2019 | ROOF NAILING | BJONES | Approved | |
01/07/2019 | EXT METAL CLIPS/EXT SHEATHING | BJONES | Approved | |
01/14/2019 | BUILDING ABOVE CEILING | DQUINN | Approved | |
01/17/2019 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
01/18/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
01/18/2019 | PLUMBING - ROOF DRAINS | DQUINN | Approved | |
01/18/2019 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
01/23/2019 | BUILDING - PROGRESS | BJONES | Approved | |
02/01/2019 | STUCCO MESH | DQUINN | Approved | |
02/14/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
02/14/2019 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | Clear eco |
02/20/2019 | MECHANICAL - HOODS | DQUINN | Approved | |
02/20/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
02/26/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
02/26/2019 | PLUMBING - PROGRESS | DMUNIZ | Approved | Kitchen Plumbing ok. CLEAR GAS |
02/26/2019 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | kitchen above grid ELECTRIC ok. |
03/14/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
03/14/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
03/14/2019 | FIRE - KITCHEN EXH HOOD FINAL | gsereno1 | Approved | |
03/14/2019 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
03/14/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
03/14/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
03/14/2019 | ELECTRIC - PROGRESS | DQUINN | Approved | |
03/14/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
03/18/2019 | FIRE - FINAL | CBASALDUA | Approved | |
04/02/2019 | CERTIFICATE OF OCCUPANCY | RLEDONNE | Approved | |
04/02/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
04/02/2019 | CERTIFICATE OF OCCUPANCY | ESTEVENS | Approved | Approve c of o upon final of engineering |
04/02/2019 | BUILDING - FINAL | ESTEVENS | Approved | Approve c of o upon final of engineering |