Permit: T18CM05242
Permit Details
Apply Date:
07/05/2018
Applicant:
SOLAR GAIN
Description:
SOLAR
Contractors:
- SOLAR GAIN
Permit Reviews
Permit Number - T18CM05242
Permit Status: Final
Permit Description: SOLAR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/05/2018 | PLANS OK TO SUBMIT - COMM | 07/06/2018 | COMPLETED |
| 07/06/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/02/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05242
Permit Status: Final
Permit Description: SOLAR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM05242
Permit Description: SOLAR
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/18/2018 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 10/18/2018 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 10/18/2018 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 10/19/2018 | ELECTRIC - FINAL | MHASSAN | Approved | OK TO CLEAR SOLAR, DGC |
| 10/19/2018 | ELECTRIC - UFER | MHASSAN | Approved | |
| 10/19/2018 | BUILDING - FINAL | MHASSAN | Approved | |
| 10/19/2018 | FRAMING | MHASSAN | Approved | |
| 10/22/2018 | TEP CLEARANCE - AM | BJONES | Approved | DGC |