Permit: T18CM05240
Permit Details
Apply Date:
07/05/2018
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT90817 T17-M0036
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM05240
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/05/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/05/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM05240
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM05240
Permit Description: SFR RICHT90817 T17-M0036
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/17/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
07/17/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
07/30/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | IVRS - Inspection :* |
07/30/2018 | BUILDING PRE-SLAB | MHASSAN1 | Approved | IVRS - Inspection :* |
07/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | IVRS - Inspection :* |
08/13/2018 | ROOF NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
08/13/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
08/30/2018 | MECHANICAL - INTERMEDIATE | GWest | Approved | |
08/30/2018 | PLUMBING - YARD WTR LINE/TEST | GWest | Approved | |
08/30/2018 | PLUMBING - INTERMEDIATE | GWest | Approved | |
08/30/2018 | ELECTRIC - CONSTRUCTION POWER | GWest | Approved | TEP = TEC-Done |
08/30/2018 | ELECTRIC - CABLE DROP | GWest | Approved | |
08/30/2018 | ELECTRIC - INTERMEDIATE | GWest | Approved | |
08/30/2018 | ELECTRIC - UFER | GWest | Approved | |
08/30/2018 | U VALUE FOR WINDOW | GWest | Approved | |
08/30/2018 | STUCCO MESH | GWest | Approved | |
08/30/2018 | FRAMING | GWest | Approved | |
08/31/2018 | PLUMBING - GAS PRESSURE TEST | GWest | Approved | SW Gas Clearance was completed for a New Connect. |
08/31/2018 | TEP CLEARANCE - AM | GWEST | Approved | TEC |
09/14/2018 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
10/18/2018 | GAS CLEARANCE | MHASSAN | Approved | RESENT PER SW GAS REQ (REC'D EMAIL FORM SUSAN MONTES) |
10/22/2018 | MECHANICAL - FINAL | TVALENCIA | Approved | |
10/22/2018 | PLUMBING - FINAL | TVALENCIA | Approved | |
10/22/2018 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
10/22/2018 | ELECTRIC - FINAL | TVALENCIA | Approved | |
10/22/2018 | BUILDING - FINAL | TVALENCIA | Approved |