Apply Date:
07/03/2018
Applicant:
OAK CREEK HOMES LLC
Description:
SFR OAKC165918 T18-M0038
Contractors:
- OAK CREEK HOMES LLC
Outstanding Activity Conditions
Permit Number - T18CM05204
Permit Status: C of o
Permit Description: SFR OAKC165918 T18-M0038
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/03/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05204
Permit Description: SFR OAKC165918 T18-M0038
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2018 | ROOF NAILING | JBURGE | Approved | |
| 07/11/2018 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 07/11/2018 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 07/11/2018 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
| 07/11/2018 | FRAMING | JBURGE | Approved | |
| 07/11/2018 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
| 08/08/2018 | SHEET ROCK NAILING | JBURGE | Approved | |
| 08/08/2018 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 08/08/2018 | STUCCO MESH | JBURGE | Approved | |
| 10/04/2018 | PLUMBING - PROGRESS | JBURGE | Approved | Domestic Water line: 1" |
| 10/04/2018 | SITE - SEWER | JBURGE | Approved | |
| 10/04/2018 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | |
| 10/24/2018 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 10/24/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
| 10/24/2018 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
| 10/24/2018 | ELECTRIC - PROGRESS | JBURGE | Approved | |
| 10/24/2018 | ELECTRIC - UNDERGROUND | JBURGE | Approved | |
| 10/24/2018 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
| 10/25/2018 | TEP CLEARANCE - AM | JBURGE | Approved | ECO |
| 11/07/2018 | ELECTRIC - TEMPORARY SERVICE | JBURGE | Approved | Units 1 &2 Ok to energize systems |
| 01/25/2019 | PLUMBING - PRE SLAB | JBURGE | Approved | approved upon 3090 approval from JBURGE |
| 01/25/2019 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | approved upon 3090 approval from JBURGE |
| 01/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | approved upon 1090 approval from JBURGE |
| 01/25/2019 | BUILDING PRE-SLAB | JBURGE | Approved | approved upon 1090 approval from JBURGE |
| 01/25/2019 | ELECTRIC - UFER | JBURGE | Approved | approved upon 2090 approval from JBURGE 10/24 |
| 01/25/2019 | BUILDING - FINAL | JBURGE | Approved | |
| 01/25/2019 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | |
| 01/25/2019 | MECHANICAL - FINAL | JBURGE | Approved | |
| 01/25/2019 | MECHANICAL - PROGRESS | JBURGE | Approved | |
| 01/25/2019 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | |
| 01/25/2019 | PLUMBING - FINAL | JBURGE | Approved | |
| 01/25/2019 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
| 01/25/2019 | BUILDING - PROGRESS | JBURGE | Approved | |
| 01/25/2019 | BUILDING ABOVE CEILING | JBURGE | Approved |