Permit: T18CM05193
Permit Details
Apply Date:
07/03/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
STORAGE
Architects:
- SWAIM, PHILLIP ELLIOTT
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T18CM05193
Permit Status: C of o
Permit Description: STORAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/03/2018 | PLANS OK TO SUBMIT - COMM | 07/11/2018 | COMPLETED |
07/11/2018 | COMMERCIAL - NEW | 09/20/2018 | COMPLETED |
09/20/2018 | COMMERCIAL - NEW | 11/02/2018 | COMPLETED |
11/02/2018 | RESUBMITTAL | 11/02/2018 | COMPLETED |
11/02/2018 | OTHER | 11/16/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05193
Permit Status: C of o
Permit Description: STORAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/03/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05193
Permit Description: STORAGE
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/30/2019 | BUILDING PRE-SLAB | BJONES | Approved | spoke to Bill via phone |
09/13/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
11/27/2019 | TEP CLEARANCE - PM | JCLAXTON | Approved | CODE ECO |
12/06/2019 | BUILDING - PROGRESS | JCLAXTON | Approved | |
12/12/2019 | FIRE - FINAL | JPEELDAVIS | Approved | |
12/12/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
12/12/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
12/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | JCLAXTON | Approved | |
12/12/2019 | PLUMBING - INTERMEDIATE | JCLAXTON | Approved | |
12/12/2019 | MECHANICAL - FINAL | JCLAXTON | Approved | |
12/12/2019 | MECHANICAL - INTERMEDIATE | JCLAXTON | Approved | |
12/12/2019 | OUTDOOR LIGHTING FINAL | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - CONSTRUCTION POWER | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - TEMP POWER FOR TEST | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - OUTDOOR LIGHTING | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - SERVICE UPGRADE | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - PROGRESS | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - ABOVE CEILING | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - INTERMEDIATE | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - UNDERGROUND | JCLAXTON | Approved | |
12/12/2019 | ELECTRIC - UFER | JCLAXTON | Approved | |
12/12/2019 | BUILDING ABOVE CEILING | JCLAXTON | Approved | |
12/12/2019 | FRAMING | JCLAXTON | Approved | |
12/12/2019 | ROOF NAILING | JCLAXTON | Approved | |
12/12/2019 | REINFORCED MASONRY PRE-GROUT | JCLAXTON | Approved | |
12/12/2019 | EXT METAL CLIPS/EXT SHEATHING | JCLAXTON | Approved | |
12/13/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
12/13/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
12/23/2019 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved | |
12/23/2019 | ELECTRIC - FINAL | AQUIROZ | Approved | |
12/23/2019 | BUILDING - FINAL | AQUIROZ | Approved |