Permit: T18CM05173
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4755 S CALLE SANTA CRUZ
Address NEW:
4755 S CALLE SANTA CRUZ
Apply Date:
07/02/2018
Applicant:
MITCH LORENZ - ML2 MANAGMENT
Description:
FITNESS CENTER
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T18CM05173
Permit Status: C of o
Permit Description: FITNESS CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/02/2018 | PLANS OK TO SUBMIT - COMM | 07/02/2018 | COMPLETED |
| 07/02/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 12/14/2018 | COMPLETED |
| 08/08/2018 | POST 3RD PARTY REVIEW | 12/14/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05173
Permit Status: C of o
Permit Description: FITNESS CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05173
Permit Description: FITNESS CENTER
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2018 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | system #1 joints at hard duct sealed and ok to insulate |
| 09/12/2018 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | system #1 joints at hard duct sealed and ok to insulate |
| 09/18/2018 | PLUMBING - PRE SLAB | RCAMACHO | Approved | Rtu 4 all seams sealed ok to insulate |
| 09/18/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | Rtu 4 all seams sealed ok to insulate |
| 11/07/2018 | SHEET ROCK NAILING | MRAMBER | Approved | |
| 11/13/2018 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/13/2018 | FRAMING | DMCCARTHY | Approved | |
| 11/20/2018 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | SWG, called in at 12:52 PM. |
| 11/21/2018 | GAS CLEARANCE | RCHANDLER | Approved | |
| 11/29/2018 | ELECTRIC - ABOVE CEILING | DMCCARTHY | Approved | BMEP ABOVE CEILING IN PLANET FITNESS |
| 11/29/2018 | BUILDING ABOVE CEILING | DMCCARTHY | Approved | BMEP ABOVE CEILING IN PLANET FITNESS |
| 11/29/2018 | MECHANICAL - ABOVE CEILING | DMCCARTHY | Approved | BMEP ABOVE CEILING IN PLANET FITNESS |
| 11/29/2018 | PLUMBING - ABOVE CEILING | DMCCARTHY | Approved | BMEP ABOVE CEILING IN PLANET FITNESS |
| 12/10/2018 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 12/10/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 12/10/2018 | MECHANICAL - FINAL | RSHERRY | Approved | Review of balance report completed |
| 12/10/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 12/10/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 12/10/2018 | MECHANICAL - FINAL | RCAMACHO | Approved | Pending air balance report |
| 12/13/2018 | PLUMBING - FINAL | RCAMACHO | Approved | pending fire final and All certs |
| 12/13/2018 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | pending fire final and All certs |
| 12/13/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | pending fire final and All certs |
| 12/13/2018 | FIRE - FINAL | gsereno1 | Approved | |
| 12/13/2018 | BUILDING - FINAL | RCAMACHO | Approved | Pending fire approval and all certs |
| 12/13/2018 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | |
| 01/15/2019 | CERTIFICATE OF OCCUPANCY | RCAMACHO | Approved |