Permit: T18CM05035
Permit Details
Apply Date:
06/27/2018
Applicant:
MAHER, JOSEPH SAID JR
Description:
ADA PLATFORM LIFT INSTALL
Architects:
- MAHER, JOSEPH SAID JR
Contractors:
- LE COCQ CONSTRUCTION COMPANY INC
Permit Reviews
Permit Number - T18CM05035
Permit Status: L of c
Permit Description: ADA PLATFORM LIFT INSTALL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/27/2018 | PLANS OK TO SUBMIT - 3RD PARTY | 06/27/2018 | COMPLETED |
06/27/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/19/2018 | COMPLETED |
07/19/2018 | POST 3RD PARTY REVIEW | 05/31/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05035
Permit Status: L of c
Permit Description: ADA PLATFORM LIFT INSTALL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM05035
Permit Description: ADA PLATFORM LIFT INSTALL
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
10/22/2018 | BUILDING - FINAL | MRAMBER | Approved | PENDING FIRE FINAL |
10/22/2018 | ELECTRIC - FINAL | MRAMBER | Approved | |
10/22/2018 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | |
10/22/2018 | LANDSCAPE - FINAL | MRAMBER | Approved | |
10/22/2018 | FRAMING | MRAMBER | Approved | |
10/22/2018 | STEM WALL/RETAINING WALL | MRAMBER | Approved | Footer poured without inspection |
10/26/2018 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
10/26/2018 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
02/15/2019 | NPPO - FINAL | BBENEDON | Approved | |
02/15/2019 | SIGN - FINAL | BBENEDON | Approved | |
02/15/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
02/18/2019 | RIGHT OF WAY - FINAL | DR | Approved | |
05/08/2019 | FIRE - FINAL | JPEELDAVIS | Approved |