Permit: T18CM05030
Permit Details
Apply Date:
06/27/2018
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LEN5080 T17-M0019
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM05030
Permit Status: Final
Permit Description: SFR LEN5080 T17-M0019
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/27/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 06/27/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05030
Permit Status: Final
Permit Description: SFR LEN5080 T17-M0019
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM05030
Permit Description: SFR LEN5080 T17-M0019
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2018 | PLUMBING - SEWER HCS CONNECT | RCAMACH1 | Approved | IVRS - Inspection :* |
| 07/31/2018 | PLUMBING - YARD WTR LINE/TEST | RCAMACH1 | Approved | IVRS - Inspection :* |
| 07/31/2018 | PLUMBING - ROUGH, SOIL | RCAMACH1 | Approved | IVRS - Inspection :* |
| 08/17/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 10/04/2018 | ROOF NAILING | ESTEVENS | Approved | |
| 10/09/2018 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | |
| 11/14/2018 | ELECTRIC - CONSTRUCTION POWER | DMCCARTHY | Approved | ECO OK TO ENERGIZE CALLED TEP FOR 3 ADDRESSES THIS STREET |
| 11/14/2018 | ELECTRIC - CABLE DROP | DMCCARTHY | Approved | ECO OK TO ENERGIZE CALLED TEP FOR 3 ADDRESSES THIS STREET |
| 11/15/2018 | TEP CLEARANCE - AM | DMCCARTHY | Approved | ECO |
| 11/20/2018 | PLUMBING - GAS PRESSURE TEST | DMCCARTHY | Approved | |
| 11/20/2018 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/20/2018 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/20/2018 | U VALUE FOR WINDOW | DMCCARTHY | Approved | |
| 11/20/2018 | STUCCO MESH | DMCCARTHY | Approved | |
| 11/20/2018 | FRAMING | DMCCARTHY | Approved | |
| 11/21/2018 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 12/07/2018 | SHEET ROCK NAILING | DMCCARTHY | Approved | |
| 02/14/2019 | GAS CLEARANCE | TVALENCIA | Approved | |
| 02/14/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | Clear gas meter |
| 02/14/2019 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
| 02/14/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 02/14/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 02/27/2019 | BUILDING - FINAL | MHASSAN | Approved | |
| 02/27/2019 | PLUMBING - FINAL | MHASSAN | Approved |