Permit: T18CM04687
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
3675 E BRITANNIA DR
Address NEW:
3675 E BRITANNIA DR
Apply Date:
06/15/2018
Applicant:
TED MOELLER
Description:
TI: WAREHOUSE/OFFICE MEZZANINE ADDITION
Architects:
- HAGEDON, BRIAN GEORGE
Permit Reviews
Permit Number - T18CM04687
Permit Status: L of c
Permit Description: TI: WAREHOUSE/OFFICE MEZZANINE ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/15/2018 | PLANS OK TO SUBMIT - COMM | 06/15/2018 | COMPLETED |
| 07/30/2018 | COMMERCIAL - TI | 08/08/2018 | COMPLETED |
| 08/08/2018 | RESUBMITTAL | 01/15/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04687
Permit Status: L of c
Permit Description: TI: WAREHOUSE/OFFICE MEZZANINE ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/15/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM04687
Permit Description: TI: WAREHOUSE/OFFICE MEZZANINE ADDITION
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/09/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 04/11/2019 | ELECTRIC - ABOVE CEILING | AKLEINSORGE | Approved | |
| 04/11/2019 | BUILDING ABOVE CEILING | AKLEINSORGE | Approved | |
| 04/11/2019 | FRAMING | AKLEINSORGE | Approved | Framing around electrical chases through mezzanine addition |
| 04/11/2019 | ELECTRIC - INTERMEDIATE | AKLEINSORGE | Approved | Lighting under mezzanine addition |
| 05/30/2019 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
| 05/30/2019 | MECHANICAL - INTERMEDIATE | AKLEINSORGE | Approved | |
| 05/30/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | All corrections complete |
| 05/30/2019 | BUILDING - PROGRESS | AKLEINSORGE | Approved | |
| 05/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | No more work done since inspection on 02/15/19 |
| 06/06/2019 | BUILDING - FINAL | MHASSAN | Approved | pending fire approval, engineering’s approval and all special inspection reports being submitted. |
| 06/06/2019 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 09/05/2019 | FIRE - FINAL | CBASALDUA | Approved | |
| 09/05/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved |