Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
7250 S TUCSON BL
Address NEW:
7250 S TUCSON BL
Apply Date:
06/07/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: DUNKIN DONUT
Architects:
  • FUENTEVILLA, MIGUEL RAUL
Contractors:
  • MW MORRISSEY CONSTRUCTION LLC

Permit Reviews

Permit Number - T18CM04471
Permit Status: C of o
Permit Description: TI: DUNKIN DONUT
Start Date Submittal Complete Date Status  
06/07/2018 PLANS OK TO SUBMIT - COMM 06/08/2018 COMPLETED Review Details
06/08/2018 3RD PARTY REVIEW - COMMERCIAL TI 07/09/2018 COMPLETED Review Details
07/09/2018 POST 3RD PARTY REVIEW 07/16/2018 COMPLETED Review Details
08/27/2018 3RD PARTY REVIEW - REVISION/OTHER 08/31/2018 COMPLETED Review Details
11/23/2018 3RD PARTY REVIEW - REVISION/OTHER 11/26/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM04471
Permit Status: C of o
Permit Description: TI: DUNKIN DONUT
Total Outstanding Activity Conditions - 1
Date Name
06/07/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM04471
Permit Description: TI: DUNKIN DONUT
Total Completed Inspections - 24
Date Description Inspector Results Comments
10/26/2018 MECHANICAL - ABOVE CEILING MRAMBER Approved
10/26/2018 MECHANICAL - INTERMEDIATE MRAMBER Approved
10/26/2018 SHEET ROCK NAILING MRAMBER Approved
10/26/2018 PLUMBING - ABOVE CEILING MRAMBER Approved
10/26/2018 PLUMBING - PRE SLAB MRAMBER Approved
10/26/2018 ELECTRIC - ABOVE CEILING MRAMBER Approved
10/26/2018 PLUMBING - INTERMEDIATE MRAMBER Approved
10/26/2018 BUILDING ABOVE CEILING MRAMBER Approved
10/26/2018 FRAMING MRAMBER Approved
11/20/2018 ELECTRIC - INTERMEDIATE RCAMACHO Approved APPROVED PER 2090 ELECTRIC FINAL
11/20/2018 ELECTRIC - FINAL RCAMACHO Approved
11/20/2018 ELECTRIC - SERVICE UPGRADE RCAMACHO Approved
11/20/2018 BUILDING PRE-SLAB RCAMACHO Approved
11/20/2018 NPPO - FINAL BBENEDON Approved
11/20/2018 SIGN - FINAL BBENEDON Approved
11/20/2018 LANDSCAPE - FINAL BBENEDON Approved
11/20/2018 ENGINEERING - FINAL BBENEDON Approved
11/20/2018 FIRE - FINAL gsereno1 Approved
11/20/2018 FIRE - ALARM FINAL gsereno1 Approved
11/20/2018 FIRE SPKLR - FINAL gsereno1 Approved
11/26/2018 RIGHT OF WAY - FINAL RSHERRY Approved
11/26/2018 BUILDING - FINAL RSHERRY Approved
11/26/2018 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPOR COMPLETED
11/26/2018 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER CHLORINATION REPORT COMPLETED