Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM04471
Permit Details
Apply Date:
06/07/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: DUNKIN DONUT
Architects:
- FUENTEVILLA, MIGUEL RAUL
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM04471
Permit Status: C of o
Permit Description: TI: DUNKIN DONUT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/07/2018 | PLANS OK TO SUBMIT - COMM | 06/08/2018 | COMPLETED |
06/08/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/09/2018 | COMPLETED |
07/09/2018 | POST 3RD PARTY REVIEW | 07/16/2018 | COMPLETED |
08/27/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 08/31/2018 | COMPLETED |
11/23/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 11/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04471
Permit Status: C of o
Permit Description: TI: DUNKIN DONUT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/07/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM04471
Permit Description: TI: DUNKIN DONUT
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2018 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
10/26/2018 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
10/26/2018 | SHEET ROCK NAILING | MRAMBER | Approved | |
10/26/2018 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
10/26/2018 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
10/26/2018 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | |
10/26/2018 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
10/26/2018 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
10/26/2018 | FRAMING | MRAMBER | Approved | |
11/20/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | APPROVED PER 2090 ELECTRIC FINAL |
11/20/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | |
11/20/2018 | ELECTRIC - SERVICE UPGRADE | RCAMACHO | Approved | |
11/20/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
11/20/2018 | NPPO - FINAL | BBENEDON | Approved | |
11/20/2018 | SIGN - FINAL | BBENEDON | Approved | |
11/20/2018 | LANDSCAPE - FINAL | BBENEDON | Approved | |
11/20/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
11/20/2018 | FIRE - FINAL | gsereno1 | Approved | |
11/20/2018 | FIRE - ALARM FINAL | gsereno1 | Approved | |
11/20/2018 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
11/26/2018 | RIGHT OF WAY - FINAL | RSHERRY | Approved | |
11/26/2018 | BUILDING - FINAL | RSHERRY | Approved | |
11/26/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPOR COMPLETED |
11/26/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |