Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
9330 E GOLF LINKS RD
Apply Date:
06/06/2018
Applicant:
MIKE HILLS
Description:
RESTURANT
Contractors:
  • MW MORRISSEY CONSTRUCTION LLC

Permit Reviews

Permit Number - T18CM04433
Permit Status: C of o
Permit Description: RESTURANT
Start Date Submittal Complete Date Status  
02/21/2019 REVISION - - 2ND 02/21/2019 COMPLETED Review Details
06/06/2018 PLANS OK TO SUBMIT - COMM 06/08/2018 COMPLETED Review Details
06/08/2018 COMMERCIAL - NEW 07/30/2018 COMPLETED Review Details
08/01/2018 RESUBMITTAL - TI ALL 09/06/2018 COMPLETED Review Details
09/20/2018 COMMERCIAL - TI 11/21/2018 COMPLETED Review Details
11/21/2018 REVISION - - 1ST 11/27/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM04433
Permit Status: C of o
Permit Description: RESTURANT
Total Outstanding Activity Conditions - 1
Date Name
06/06/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM04433
Permit Description: RESTURANT
Total Completed Inspections - 42
Date Description Inspector Results Comments
08/09/2018 PLUMBING - FINAL RSHERRY Approved WATER CHLORINATION REPORT REQUIRED
09/20/2018 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE REPORT REQUIRED
12/14/2018 PLUMBING - ROUGH, SOIL BJONES Approved 1/12” PVC water service
12/19/2018 ELECTRIC - UNDERGROUND BJONES Approved Up to within 10’ of building
12/19/2018 ELECTRIC - UFER BJONES Approved
12/19/2018 EXCAVATION/LAYOUT REBAR & ZON BJONES Approved
12/26/2018 SITE - SEWER BJONES Approved PVC Sewer Line
12/26/2018 PLUMBING - SEWER HCS CONNECT BJONES Approved Clean-out riser not set at this inspection
01/04/2019 STEM WALL/RETAINING WALL BJONES Approved #4 Vertical Rebar 4’OC and 2-Horizontal per plan
01/29/2019 BUILDING PRE-SLAB BJONES Approved Slab grade with 4" Mesh
01/30/2019 ELECTRIC - PROGRESS BJONES Approved Light pole bases per detail by E Masitis, 4 #5 Vert with #3 ties 12”OC.
Grounding per light pole manufacturer 20’ #4 Copper
02/05/2019 PLUMBING - BACK WATER VALVE BJONES Approved
02/13/2019 REINFORCED MASONRY PRE-GROUT BJONES Approved Screen wall 2#4 bond beam and #4 vertical rebar each cell
03/05/2019 ROOF NAILING DQUINN Approved
03/05/2019 EXT METAL CLIPS/EXT SHEATHING DQUINN Approved
03/07/2019 ELECTRIC - ABOVE CEILING BJONES Approved Mechanical and electric only in outside eve not building
03/11/2019 PLUMBING - ROOF DRAINS BJONES Approved Roof rain leaders and secondaries
03/15/2019 MECHANICAL - INTERMEDIATE GWEST Approved
03/15/2019 MECHANICAL - ABOVE CEILING GWEST Approved
03/15/2019 PLUMBING - INTERMEDIATE GWEST Approved
03/15/2019 ELECTRIC - INTERMEDIATE GWEST Approved
03/15/2019 FRAMING GWEST Approved
04/05/2019 U VALUE FOR WINDOW DQUINN Approved
04/05/2019 PLUMBING - YARD WTR LINE/TEST DQUINN Approved
04/05/2019 PLUMBING - ABOVE CEILING DQUINN Approved
04/05/2019 BUILDING ABOVE CEILING DQUINN Approved
04/11/2019 TEP CLEARANCE - PM GWEST Approved CODE TEC
04/11/2019 ELECTRIC - TEMPORARY SERVICE GWEST Approved New 120/208, 400amp service
TEP Clearance, TEC
04/18/2019 FIRE - ALARM FINAL Mross Approved
04/18/2019 FIRE SPKLR - FINAL Mross Approved
05/09/2019 PLUMBING - PROGRESS DQUINN Approved approved upon 3090 approval
05/09/2019 OUTDOOR LIGHTING FINAL DQUINN Approved
05/09/2019 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved
05/09/2019 ELECTRIC - CONSTRUCTION POWER DQUINN Approved
05/09/2019 BUILDING - PROGRESS DQUINN Approved
05/09/2019 ELECTRIC - FINAL DQUINN Approved
05/10/2019 FIRE - FINAL gsereno1 Approved
05/17/2019 HEALTH DEPT - FINAL 724-7908 JKINCAID Approved
06/21/2019 BUILDING - FINAL DQUINN Approved
06/21/2019 ENGINEERING - FINAL RLEDONNE Approved
06/24/2019 CERTIFICATE OF OCCUPANCY DQUINN Approved PER 1090
06/24/2019 CERTIFICATE OF OCCUPANCY DQUINN Approved