Permit: T18CM04341
Permit Details
Apply Date:
06/05/2018
Applicant:
G AND J DEVELOPMENT INC ,
Description:
TI: MEDICAL OFFICE
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T18CM04341
Permit Status: Final
Permit Description: TI: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/05/2018 | COMMERCIAL - TI | 06/05/2018 | COMPLETED |
06/05/2018 | COMMERCIAL - TI | 06/29/2018 | COMPLETED |
06/29/2018 | REVISION - - 1ST | 06/29/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04341
Permit Status: Final
Permit Description: TI: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM04341
Permit Description: TI: MEDICAL OFFICE
Total Completed Inspections - 15
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/19/2018 | PLUMBING - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
07/19/2018 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
08/28/2018 | FRAMING | BJONES1 | Approved | IVRS - Inspection :* |
08/28/2018 | ELECTRIC - INTERMEDIATE | BJONES1 | Approved | IVRS - Inspection :* |
10/01/2018 | PLUMBING - FINAL | BJONES | Approved | approved by inspector, but water report never approved |
10/03/2018 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | |
10/03/2018 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
10/03/2018 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | |
10/25/2018 | BUILDING - FINAL | MHASSAN | Approved | make sure to clear storage stuff out of ADA restroom. Address mop sink as it sits off the wall and water can get trapped behind and around it. Okay for TCO |
10/25/2018 | MECHANICAL - FINAL | MHASSAN | Approved | pending Air Balance report which is pending additional work in waiting room area |
10/25/2018 | ELECTRIC - FINAL | MHASSAN | Approved | |
10/25/2018 | BUILDING - PROGRESS | MHASSAN | Approved | still need to inspect waiting room area. This inspection will be used for the intermediates in that area |
10/25/2018 | FIRE SPKLR - FINAL | jvincent | Approved | |
11/05/2018 | FIRE - FINAL | jvincent | Approved | |
05/02/2019 | BUILDING ABOVE CEILING | MRAMBER | Approved |