Permit: T18CM04231
Permit Details
Apply Date:
05/31/2018
Applicant:
INAI ANZUETO
Description:
CHANGE GARAGE INTO BEDROOM/ REWIRE HOUSE AND 200 AMP UPGRADE
Permit Reviews
Permit Number - T18CM04231
Permit Status: Final
Permit Description: CHANGE GARAGE INTO BEDROOM/ REWIRE HOUSE AND 200 AMP UPGRADE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/31/2018 | PLANS OK TO SUBMIT - RES | 06/11/2018 | COMPLETED |
| 09/26/2018 | REVISION - - 1ST | 09/26/2018 | COMPLETED |
| 12/18/2018 | REVISION - - 2ND | 12/18/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04231
Permit Status: Final
Permit Description: CHANGE GARAGE INTO BEDROOM/ REWIRE HOUSE AND 200 AMP UPGRADE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/31/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM04231
Permit Description: CHANGE GARAGE INTO BEDROOM/ REWIRE HOUSE AND 200 AMP UPGRADE
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 01/11/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 01/11/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 01/11/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 01/15/2019 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | |
| 01/15/2019 | RESIDENTIAL INTERMEDIATE | RCHANDLER | Approved | Including gas pressure |
| 01/15/2019 | FRAMING | RCHANDLER | Approved | |
| 02/21/2019 | GAS CLEARANCE | RCHANDLER | Approved | CODE INCR |
| 02/21/2019 | TEP CLEARANCE - AM | RCHANDLER | Approved | CODE INCR |
| 03/07/2019 | ROOF NAILING | DQUINN | Approved | approved upon 1090 approval from DQUINN |
| 03/07/2019 | MECHANICAL - FINAL | DQUINN | Approved | |
| 03/07/2019 | PLUMBING - FINAL | DQUINN | Approved | |
| 03/07/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 03/07/2019 | BUILDING - FINAL | DQUINN | Approved |