Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
330 W FORT LOWELL RD
Apply Date:
05/16/2018
Applicant:
EXA ARCHITECTS
Description:
CARPET STORE
Architects:
  • JOSE L CEJA
Contractors:
  • EPSTEIN CONSTRUCTION L L C

Permit Reviews

Permit Number - T18CM03789
Permit Status: C of o
Permit Description: CARPET STORE
Start Date Submittal Complete Date Status  
05/16/2018 COMMERCIAL - TI 05/17/2018 COMPLETED Review Details
05/17/2018 RESUBMITTAL 07/06/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM03789
Permit Status: C of o
Permit Description: CARPET STORE
Total Outstanding Activity Conditions - 1
Date Name
05/16/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM03789
Permit Description: CARPET STORE
Total Completed Inspections - 16
Date Description Inspector Results Comments
08/17/2018 PLUMBING - INTERMEDIATE ESTEVEN1 Approved APPROVED
08/17/2018 FRAMING ESTEVEN1 Approved APPROVED
08/17/2018 ELECTRIC - INTERMEDIATE ESTEVEN1 Approved APPROVED
09/05/2018 FIRE - FINAL CBASALDUA Approved
09/05/2018 FIRE SPKLR - FINAL CBASALDUA Approved
09/05/2018 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
09/05/2018 BUILDING ABOVE CEILING ESTEVENS Approved
09/05/2018 PLUMBING - FINAL ESTEVENS Approved
09/05/2018 ELECTRIC - FINAL ESTEVENS Approved
09/05/2018 MECHANICAL - FINAL ESTEVENS Approved
09/05/2018 MECHANICAL - INTERMEDIATE ESTEVENS Approved
09/05/2018 PLUMBING - ABOVE CEILING ESTEVENS Approved
09/05/2018 MECHANICAL - ABOVE CEILING ESTEVENS Approved
09/05/2018 ELECTRIC - ABOVE CEILING ESTEVENS Approved
09/12/2018 CERTIFICATE OF OCCUPANCY ESTEVENS Approved
09/12/2018 BUILDING - FINAL ESTEVENS Approved