Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
05/09/2018
Applicant:
MERITAGE HOMES CONSTRUCTION INC *** APA***
Description:
SFR PLAN2302380 T18-M0015
Contractors:
  • MERITAGE HOMES CONSTRUCTION INC *** APA***

Permit Reviews

Permit Number - T18CM03567
Permit Status: Final
Permit Description: SFR PLAN2302380 T18-M0015
Start Date Submittal Complete Date Status  
05/09/2018 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 05/09/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM03567
Permit Status: Final
Permit Description: SFR PLAN2302380 T18-M0015
Total Outstanding Activity Conditions - 1
Date Name
05/09/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM03567
Permit Description: SFR PLAN2302380 T18-M0015
Total Completed Inspections - 25
Date Description Inspector Results Comments
06/08/2018 PLUMBING - SEWER HCS CONNECT MHASSAN1 Approved
06/08/2018 PLUMBING - ROUGH, SOIL MHASSAN1 Approved
06/19/2018 ELECTRIC - UNDERGROUND MHASSAN1 Approved
06/19/2018 BUILDING PRE-SLAB MHASSAN1 Approved
06/19/2018 EXCAVATION/LAYOUT REBAR & ZON MHASSAN1 Approved
07/06/2018 ROOF NAILING MHASSAN1 Approved
07/06/2018 EXT METAL CLIPS/EXT SHEATHING MHASSAN1 Approved ADD MISSING H2.5 UPSTAIRS. PUT SPACING FOR DEFLECTION UNDER A46A. ADD MISSING SHEAR WALL BY FRONT ENTRY DOWNSTAIRS.
07/31/2018 MECHANICAL - INTERMEDIATE MHASSAN1 Approved
07/31/2018 PLUMBING - YARD WTR LINE/TEST MHASSAN1 Approved
07/31/2018 ELECTRIC - CONSTRUCTION POWER MHASSAN1 Approved OK TO CLEAR ELECTRIC, TMPP
07/31/2018 ELECTRIC - INTERMEDIATE MHASSAN1 Approved
07/31/2018 U VALUE FOR WINDOW MHASSAN1 Approved
07/31/2018 STUCCO MESH MHASSAN1 Approved
07/31/2018 FRAMING MHASSAN1 Approved
08/01/2018 TEP CLEARANCE - AM MHASSAN Approved TMPP
08/19/2018 PLUMBING - INTERMEDIATE BJONES1 Approved IVRS - Inspection :*
08/27/2018 SHEET ROCK NAILING GWest Approved
10/11/2018 GAS CLEARANCE TVALENCIA Approved
10/18/2018 MECHANICAL - FINAL TVALENCIA Approved
10/18/2018 PLUMBING - FINAL TVALENCIA Approved
10/18/2018 OUTDOOR LIGHTING FINAL TVALENCIA Approved
10/18/2018 ELECTRIC - FINAL TVALENCIA Approved
10/18/2018 BUILDING - FINAL TVALENCIA Approved
10/23/2018 ELECTRIC - UFER TVALENC1 Approved
10/23/2018 PLUMBING - GAS PRESSURE TEST TVALENC1 Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW