Permit: T18CM03344
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
3065 N DASYLIRION DR
Address NEW:
3065 N DASYLIRION DR
Apply Date:
05/02/2018
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Description:
SFR PEPP124117 T17-M0062
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Outstanding Activity Conditions
Permit Number - T18CM03344
Permit Status: C of o
Permit Description: SFR PEPP124117 T17-M0062
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM03344
Permit Description: SFR PEPP124117 T17-M0062
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/15/2018 | SITE - SEWER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/15/2018 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/15/2018 | PLUMBING - YARD WTR LINE/TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/15/2018 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/25/2018 | PLUMBING - PRE SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/25/2018 | ELECTRIC - UNDERGROUND | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/25/2018 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/25/2018 | BUILDING PRE-SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/30/2018 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 07/30/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
| 07/30/2018 | ROOF NAILING | ESTEVEN1 | Approved | |
| 07/30/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | |
| 08/17/2018 | MECHANICAL - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | BUILDING - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | FRAMING | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 08/17/2018 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | APPROVED |
| 08/21/2018 | STUCCO MESH | MHASSAN1 | Approved | |
| 08/31/2018 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | CLEAR TMPP |
| 08/31/2018 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 09/04/2018 | TEP CLEARANCE - AM | BSTEVENS | Approved | TMPP |
| 10/25/2018 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | |
| 10/25/2018 | MECHANICAL - FINAL | ESTEVENS | Approved | |
| 10/25/2018 | PLUMBING - FINAL | ESTEVENS | Approved | |
| 10/26/2018 | GAS CLEARANCE | ESTEVENS | Approved | |
| 10/30/2018 | BUILDING - FINAL | ESTEVENS | Approved | |
| 10/30/2018 | ELECTRIC - FINAL | ESTEVENS | Approved |