Permit: T18CM03268
Permit Details
Apply Date:
05/01/2018
Applicant:
N/A
Description:
NEW SFR
Permit Reviews
Permit Number - T18CM03268
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/01/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 05/18/2018 | COMPLETED |
05/18/2018 | RESUBMITTAL | 06/14/2018 | COMPLETED |
06/14/2018 | REVISION - - 1ST | 07/25/2018 | COMPLETED |
08/08/2018 | REVISION - - 2ND | 08/08/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM03268
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/01/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM03268
Permit Description: NEW SFR
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/16/2018 | STEM WALL/RETAINING WALL | MHASSAN1 | Approved | |
08/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | IVRS - Inspection :* |
09/11/2018 | REINFORCED MASONRY PRE-GROUT | CTREVIL | Approved | Final grout inspection did not occur. Horizontal reinforcement required and Dave Ollanik has attested to it being installed although not inspected and has taken responsibility for any structural defincies. |
09/17/2018 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | TJI floor joists only. |
09/26/2018 | ROOF NAILING | JBURGE | Approved | OK TO DRY IN ROOF SYSTEM |
09/26/2018 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
10/03/2018 | ELECTRIC - UFER | ESTEVENS | Approved | |
10/09/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
10/09/2018 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | |
10/09/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
10/09/2018 | FRAMING | ESTEVENS | Approved | |
10/15/2018 | MECHANICAL - INTERMEDIATE | BJONES | Approved | |
10/18/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | ECO |
12/28/2018 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | Must be 12 inches below grade, need record of sewer agreement between neighbors |
12/28/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
01/04/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
02/20/2019 | MECHANICAL - FINAL | ESTEVENS | Approved | |
02/26/2019 | PLUMBING - FINAL | ESTEVENS | Approved | |
02/26/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
06/26/2019 | FLOODPLAIN INSP | DROBERTS | Approved | |
06/26/2019 | ZONING - FINAL | DROBERTS | Approved | |
06/26/2019 | ELECTRIC - FINAL | RCAMACHO | Approved | |
06/26/2019 | ELECTRIC - FINAL | DROBERTS | Approved |