Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
04/18/2018
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR T725 T16-M0063
Contractors:
  • RICHMOND AMERICAN HOMES ** APA ***

Permit Reviews

Permit Number - T18CM02896
Permit Status: Final
Permit Description: SFR T725 T16-M0063
Start Date Submittal Complete Date Status  
04/18/2018 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 04/18/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM02896
Permit Status: Final
Permit Description: SFR T725 T16-M0063
Total Outstanding Activity Conditions - 1
Date Name
04/18/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM02896
Permit Description: SFR T725 T16-M0063
Total Completed Inspections - 26
Date Description Inspector Results Comments
04/26/2018 PLUMBING - SEWER HCS CONNECT MHASSAN1 Approved
04/26/2018 PLUMBING - YARD WTR LINE/TEST MHASSAN1 Approved
04/26/2018 PLUMBING - ROUGH, SOIL MHASSAN1 Approved
05/01/2018 ELECTRIC - UNDERGROUND MHASSAN1 Approved
05/01/2018 BUILDING PRE-SLAB MHASSAN1 Approved
05/02/2018 EXCAVATION/LAYOUT REBAR & ZON MHASSAN1 Approved
05/16/2018 ROOF NAILING MHASSAN1 Approved
05/17/2018 EXT METAL CLIPS/EXT SHEATHING MHASSAN1 Approved FINISH THE MISSING NAILS ON NW CORNER SHEAR WALL 2ND FL.
06/18/2018 MECHANICAL - INTERMEDIATE MHASSAN1 Approved
06/18/2018 PLUMBING - GAS PRESSURE TEST MHASSAN1 Approved
06/18/2018 PLUMBING - INTERMEDIATE MHASSAN1 Approved
06/18/2018 ELECTRIC - CONSTRUCTION POWER MHASSAN1 Approved
06/18/2018 ELECTRIC - CABLE DROP MHASSAN1 Approved OK TO CLEAR ELECTRIC, TMPP
06/18/2018 U VALUE FOR WINDOW MHASSAN1 Approved
06/18/2018 STUCCO MESH MHASSAN1 Approved
06/19/2018 TEP CLEARANCE - AM MHASSAN Approved TMPP
06/20/2018 ELECTRIC - INTERMEDIATE MHASSAN1 Approved
06/20/2018 FRAMING MHASSAN1 Approved
06/21/2018 ELECTRIC - UFER MHASSAN1 Approved
06/27/2018 SHEET ROCK NAILING MHASSAN1 Approved
08/03/2018 PLUMBING - PROGRESS MHASSAN1 Approved OK TO CLEAR GAS FOR NEW SERVICE, SENT EMAIL INTO SW GAS
08/10/2018 MECHANICAL - FINAL TVALENC1 Approved IVRS - Inspection :*
08/10/2018 PLUMBING - FINAL TVALENC1 Approved IVRS - Inspection :*
08/10/2018 OUTDOOR LIGHTING FINAL TVALENC1 Approved IVRS - Inspection :*
08/10/2018 ELECTRIC - FINAL TVALENC1 Approved IVRS - Inspection :*
08/10/2018 BUILDING - FINAL TVALENC1 Approved IVRS - Inspection :*

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW