Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
04/16/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RESTAURANT
Contractors:
  • BARKER CONTRACTING INC **APA**

Permit Reviews

Permit Number - T18CM02757
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
04/16/2018 PLANS OK TO SUBMIT - COMM 04/19/2018 COMPLETED Review Details
04/19/2018 3RD PARTY REVIEW - COMMERCIAL TI 07/31/2018 COMPLETED Review Details
07/31/2018 3RD PARTY REVIEW - REVISION/OTHER 08/02/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM02757
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
04/16/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM02757
Permit Description: RESTAURANT
Total Completed Inspections - 35
Date Description Inspector Results Comments
06/07/2018 ELECTRIC - UNDERGROUND RCAMACHO Approved
06/28/2018 BUILDING PRE-SLAB RCAMACH1 Approved IVRS - Inspection :*
06/28/2018 BUILDING PRE-SLAB RCAMACHO Approved
07/05/2018 PLUMBING - ABOVE CEILING RCAMACH1 Approved IVRS - Inspection :*
07/05/2018 PLUMBING - GAS PRESSURE TEST RCAMACH1 Approved IVRS - Inspection :*
07/05/2018 PLUMBING - INTERMEDIATE RCAMACH1 Approved IVRS - Inspection :*
07/06/2018 MECHANICAL - ABOVE CEILING RCAMACHO Approved
07/06/2018 ELECTRIC - SERVICE UPGRADE RCAMACHO Approved ECO
OK TO ENERGIZE EXISTING SWITCHGEAR FROM SHELL
07/09/2018 TEP CLEARANCE - AM RCAMACHO Approved ECO
07/12/2018 SHEET ROCK NAILING mramber1 Approved
07/13/2018 GAS CLEARANCE RCAMACHO Approved
07/24/2018 MECHANICAL - HOODS ESTEVEN1 Approved APPROVED
07/24/2018 ELECTRIC - ABOVE CEILING ESTEVEN1 Approved APPROVED
07/24/2018 ELECTRIC - INTERMEDIATE ESTEVEN1 Approved APPROVED
07/24/2018 BUILDING ABOVE CEILING ESTEVEN1 Approved APPROVED
07/24/2018 MECHANICAL - INTERMEDIATE ESTEVEN1 Approved APPROVED
07/24/2018 FRAMING ESTEVEN1 Approved APPROVED
07/26/2018 ELECTRIC - FINAL DQUINN Approved
07/26/2018 PLUMBING - FINAL DQUINN Approved
07/26/2018 MECHANICAL - FINAL DQUINN Approved
07/26/2018 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved
07/26/2018 OUTDOOR LIGHTING FINAL DQUINN Approved
07/26/2018 PLUMBING - ROUGH, SOIL DQUINN Approved
07/26/2018 PLUMBING - PRE SLAB DQUINN Approved
07/26/2018 PLUMBING - GAS PRESS TEST FNL DQUINN Approved
07/27/2018 FIRE - KITCHEN EXH HOOD FINAL jvincent Approved
07/27/2018 FIRE SPKLR - FINAL jvincent Approved
07/30/2018 MECHANICAL - HOOD SYSTEMS ESTEVEN1 Approved APPROVED
07/31/2018 BUILDING - FINAL RSHERRY Approved REVIEW OF AIR BALANCE AND WATER CHLORINATION REPORTS COMPLETED
08/03/2018 NPPO - FINAL DROBERTS Approved
08/03/2018 SIGN - FINAL DROBERTS Approved
08/03/2018 LANDSCAPE - FINAL DROBERTS Approved
08/03/2018 ENGINEERING - FINAL DROBERTS Approved
08/03/2018 RIGHT OF WAY - FINAL PC Approved NO WORK IN ROW
08/07/2018 FIRE - FINAL jvincent Approved