Permit: T18CM02690
Permit Details
Apply Date:
04/12/2018
Applicant:
METRO TED
Description:
TI: LEASING OFFICE
Contractors:
- BEAL DERKENNE CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM02690
Permit Status: C of o
Permit Description: TI: LEASING OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/12/2018 | COMMERCIAL - TI | 04/23/2018 | COMPLETED |
04/23/2018 | COMMERCIAL - TI | 04/26/2018 | COMPLETED |
04/26/2018 | RESUBMITTAL | 05/02/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02690
Permit Status: C of o
Permit Description: TI: LEASING OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02690
Permit Description: TI: LEASING OFFICE
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/13/2018 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | |
06/13/2018 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | CANCELLED BY CUSTOMER |
06/28/2018 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
06/28/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
06/28/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
06/28/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
07/19/2018 | FRAMING | ESTEVEN1 | Approved | |
07/19/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED |
07/19/2018 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | APPROVED INCR |
07/19/2018 | ELECTRIC - TEMPORARY SERVICE | ESTEVEN1 | Approved | APPROVED INCR |
07/30/2018 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
07/31/2018 | TEP CLEARANCE - AM | BSTEVENS | Approved | 733/735 N 4TH AV INCR |
08/02/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | |
08/02/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | |
08/03/2018 | PLUMBING - FINAL | ESTEVEN1 | Approved | APPROVED |
08/03/2018 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | |
08/03/2018 | OUTDOOR LIGHTING FINAL | ESTEVEN1 | Approved | APPROVED |
08/03/2018 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
08/03/2018 | ELECTRIC - OUTDOOR LIGHTING | ESTEVEN1 | Approved | APPROVED |
08/03/2018 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | APPROVED |
08/03/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
08/07/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
08/07/2018 | FIRE - FINAL | JPEELDAVIS | Approved | Need address 12 in letters 1 inch stroke. Need to remove the slide bolts from the doors |
08/14/2018 | CERTIFICATE OF OCCUPANCY | ESTEVEN1 | Approved | APPROVED PER BUILDING FINAL |
08/14/2018 | BUILDING - FINAL | ESTEVEN1 | Approved | APPROVED PER OTHER INSPECTIONS |
08/14/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |