Permit: T18CM02664
Permit Details
Apply Date:
04/11/2018
Applicant:
N/A
Description:
OFFICE
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T18CM02664
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/11/2018 | PLANS OK TO SUBMIT - COMM | 04/11/2018 | COMPLETED |
04/11/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 04/30/2018 | COMPLETED |
04/30/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/09/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02664
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/11/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02664
Permit Description: OFFICE
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/09/2018 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | |
05/31/2018 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
05/31/2018 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
06/06/2018 | BUILDING PRE-SLAB | mramber1 | Approved | |
06/06/2018 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
06/08/2018 | SHEET ROCK NAILING | mramber1 | Approved | |
06/19/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
07/02/2018 | TEP CLEARANCE - AM | DQUINN | Approved | INCR |
07/05/2018 | MECHANICAL - HOOD SYSTEMS | BJONES1 | Approved | IVRS - Inspection :* |
07/05/2018 | MECHANICAL - ABOVE CEILING | BJONES1 | Approved | IVRS - Inspection :* |
07/05/2018 | PLUMBING - ABOVE CEILING | BJONES1 | Approved | IVRS - Inspection :* |
07/05/2018 | ELECTRIC - ABOVE CEILING | BJONES1 | Approved | IVRS - Inspection :* |
07/05/2018 | BUILDING ABOVE CEILING | BJONES1 | Approved | IVRS - Inspection :* |
07/12/2018 | ENGINEERING - FINAL | DROBERTS | Approved | CHECKED THE ADA PARKING SPACES ON THE WEST SIDE OF THIS SITE, THEY ARE LESS THAN2% IN ALL DIRECTIONS |
07/13/2018 | PLUMBING - FINAL | DQUINN | Approved | |
07/13/2018 | MECHANICAL - FINAL | DQUINN | Approved | |
07/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
07/13/2018 | FRAMING | DQUINN | Approved | |
07/13/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
07/13/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
07/13/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
07/20/2018 | CERTIFICATE OF OCCUPANCY | JEFFWEST | Approved | |
07/20/2018 | BUILDING - FINAL | JEFFWEST | Approved | |
07/20/2018 | FIRE - FINAL | GSERENO | Approved |