Permit: T18CM02565
Permit Details
Apply Date:
04/09/2018
Applicant:
VINCE CATALANO
Description:
DINING AND BAR
Contractors:
- ARIZONA SONORAN MAINTENANCE AND MECHANICAL LLC
Permit Reviews
Permit Number - T18CM02565
Permit Status: C of o
Permit Description: DINING AND BAR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2018 | COMMERCIAL - TI | 04/11/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02565
Permit Status: C of o
Permit Description: DINING AND BAR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/09/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02565
Permit Description: DINING AND BAR
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/24/2018 | FRAMING | NORTH | Approved | |
04/24/2018 | PLUMBING - INTERMEDIATE | NORTH | Approved | |
04/24/2018 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
04/24/2018 | ELECTRIC - ABOVE CEILING | NORTH | Approved | |
04/24/2018 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | doors locked, no access no one on site |
05/03/2018 | BUILDING - PROGRESS | JBURGE | Approved | |
05/03/2018 | BUILDING ABOVE CEILING | JBURGE | Approved | |
05/03/2018 | PLUMBING - PROGRESS | JBURGE | Approved | |
05/03/2018 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
05/03/2018 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
05/03/2018 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
05/03/2018 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
05/04/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
05/04/2018 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
05/07/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | Signed and approved by Chris Basaldua on May 03-2018 TFD entered by JMPD |
05/07/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | Signed and approved by Gary Sereno on May 04-2018 TFD entered by JMPD |
05/08/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT REVIEW COMPLETED |
05/08/2018 | CERTIFICATE OF OCCUPANCY | JBURGESS | Approved | APPROVAL SENT TO RECORDS |
05/08/2018 | BUILDING - FINAL | JBURGESS | Approved | APPROVAL SENT TO RECORDS |
05/08/2018 | MECHANICAL - FINAL | JBURGESS | Approved | APPROVED PER 1090 BUILDING FINAL |
05/08/2018 | PLUMBING - FINAL | JBURGESS | Approved | APPROVED PER 1090 BUILDING FINAL |
05/08/2018 | ENGINEERING - FINAL | JBURGESS | Approved | APPROVAL SENT TO RECORDS |
05/08/2018 | FIRE - FINAL | gsereno1 | Approved | Informed owner of need of a places of assembly operational permit. |