Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM02513
Permit Details
Apply Date:
04/04/2018
Applicant:
CHARLES PIFER
Description:
NEW DUPLEX
Permit Reviews
Permit Number - T18CM02513
Permit Status: C of o
Permit Description: NEW DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/04/2018 | PLANS OK TO SUBMIT - RES | 04/09/2018 | COMPLETED |
| 04/09/2018 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 05/07/2018 | COMPLETED |
| 06/06/2018 | RESUBMITTAL | 06/07/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02513
Permit Status: C of o
Permit Description: NEW DUPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/04/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02513
Permit Description: NEW DUPLEX
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | RISER HAS NO WATER FOR TEST |
| 07/25/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | COPPER WIRE CLAMPED TO REBAR ON WEST SIDE OF BUILDING. |
| 07/25/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 07/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 12/12/2018 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | 1- Firewall sheet rock nailing is okay for tape and mud |
| 12/12/2018 | FRAMING | TVALENCIA | Approved | 1- Shall call for Framing inspection with all intermediate inspections. |
| 12/12/2018 | ROOF NAILING | TVALENCIA | Approved | |
| 12/12/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 12/12/2018 | FIREWALL/FIREBARRIER/FIRESTOP | DMCCARTHY | Approved | need to inspect at framing and MEP intermediates are complete |
| 12/12/2018 | FRAMING | DMCCARTHY | Approved | cannot do framing inspection without MEP intermediates being performed at the same time |
| 12/12/2018 | ROOF NAILING | DMCCARTHY | Approved | no later |
| 12/12/2018 | EXT METAL CLIPS/EXT SHEATHING | DMCCARTHY | Approved | Middle looks good butneed ladder for roof to complete the whole exterior |
| 01/30/2019 | STUCCO MESH | TVALENCIA | Approved | |
| 02/07/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
| 02/15/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 02/15/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 02/15/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 03/22/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | TEP code is ECO |
| 07/03/2019 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
| 07/03/2019 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
| 07/03/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
| 08/13/2019 | BUILDING - FINAL | TVALENCIA | Approved | |
| 08/13/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 08/13/2019 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 08/13/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | |
| 08/14/2019 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE DGC |