Permit: T18CM02403
Permit Details
Apply Date:
04/02/2018
Applicant:
JAZMIN HINOJOSA
Description:
SFR: ADD 2 BEDROOMS AND 1 BATHROOM
Permit Reviews
Permit Number - T18CM02403
Permit Status: Final
Permit Description: SFR: ADD 2 BEDROOMS AND 1 BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/02/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/10/2018 | COMPLETED |
| 05/17/2018 | REVISION - - 1ST | 05/17/2018 | COMPLETED |
| 06/14/2018 | REVISION - - 2ND | 06/14/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM02403
Permit Status: Final
Permit Description: SFR: ADD 2 BEDROOMS AND 1 BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM02403
Permit Description: SFR: ADD 2 BEDROOMS AND 1 BATHROOM
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2018 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
| 05/18/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 05/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 06/12/2018 | ELECTRIC - SERVICE RELOCATION | ESTEVEN1 | Approved | APPROVED INCR |
| 06/12/2018 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | APPROVED INCR |
| 06/12/2018 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED INCR |
| 06/13/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 06/19/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | APPROVED |
| 06/19/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 06/19/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
| 06/19/2018 | FRAMING | ESTEVEN1 | Approved | APPROVED |
| 06/21/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 06/21/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 06/21/2018 | STUCCO MESH | ESTEVEN1 | Approved | APPROVED |
| 07/30/2018 | OUTDOOR LIGHTING FINAL | ESTEVEN1 | Approved | APPROVED |
| 07/30/2018 | MECHANICAL - FINAL | ESTEVEN1 | Approved | APPROVED |
| 07/31/2018 | PLUMBING - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 07/31/2018 | ELECTRIC - FINAL | BJONES1 | Approved | IVRS - Inspection :* |
| 07/31/2018 | BUILDING - FINAL | BJONES1 | Approved | IVRS - Inspection :* |