Permit: T18CM02309
Permit Details
Apply Date:
03/28/2018
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR PLAN3570 T17-MOO50
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM02309
Permit Status: Final
Permit Description: SFR PLAN3570 T17-MOO50
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2018 | WALK THRU - RES | 03/28/2018 | COMPLETED |
03/28/2018 | WALK THRU - RES | 03/28/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02309
Permit Status: Final
Permit Description: SFR PLAN3570 T17-MOO50
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM02309
Permit Description: SFR PLAN3570 T17-MOO50
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/01/2018 | SITE - SEWER | DFLORES2 | Approved | |
05/01/2018 | PLUMBING - SEWER HCS CONNECT | DFLORES2 | Approved | |
05/01/2018 | PLUMBING - YARD WTR LINE/TEST | DFLORES2 | Approved | |
05/01/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | |
05/07/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
05/07/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
05/07/2018 | PLUMBING - PRE SLAB | DFLORES2 | Approved | |
06/15/2018 | MECHANICAL - INTERMEDIATE | GWest | Approved | |
06/15/2018 | PLUMBING - GAS PRESS TEST FNL | GWest | Approved | |
06/15/2018 | PLUMBING - INTERMEDIATE | GWest | Approved | |
06/15/2018 | ELECTRIC - INTERMEDIATE | GWest | Approved | |
06/15/2018 | U VALUE FOR WINDOW | GWest | Approved | |
06/15/2018 | STUCCO MESH | GWest | Approved | |
06/15/2018 | ELECTRIC - TEMPORARY SERVICE | GWest | Approved | |
06/18/2018 | EXT METAL CLIPS/EXT SHEATHING | dflores2 | Approved | |
06/18/2018 | ROOF NAILING | dflores2 | Approved | |
06/18/2018 | TEP CLEARANCE - AM | GWEST | Approved | ECO |
07/13/2018 | BUILDING ABOVE CEILING | BJONES | Approved | |
07/13/2018 | FRAMING | BJONES | Approved | INSPECTED IN ERROR ON 06/15/18 |
07/16/2018 | MECHANICAL - PROGRESS | BJONES | Approved | |
07/16/2018 | MECHANICAL - ABOVE CEILING | BJONES | Approved | |
07/16/2018 | PLUMBING - PROGRESS | BJONES | Approved | |
07/16/2018 | PLUMBING - ABOVE CEILING | BJONES | Approved | |
07/16/2018 | ELECTRIC - PROGRESS | BJONES | Approved | |
07/16/2018 | ELECTRIC - ABOVE CEILING | BJONES | Approved | |
07/16/2018 | ELECTRIC - UFER | BJONES | Approved | UFER COMPLETED |
07/19/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
09/10/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | IVRS - Inspection :* |
09/10/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | IVRS - Inspection :* |
09/10/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES2 | Approved | IVRS - Inspection :* |
09/11/2018 | GAS CLEARANCE | DFLORES | Approved | |
09/20/2018 | BUILDING - FINAL | MHASSAN1 | Approved | ONLY PENDING CERTIFICATION PAPERWORK BEING TURNED IN. |
09/20/2018 | OUTDOOR LIGHTING FINAL | MHASSAN1 | Approved | |
09/20/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
09/20/2018 | BUILDING - PROGRESS | MHASSAN1 | Approved | GAS METER ALREADY INSTALLED |
09/20/2018 | PLUMBING - FINAL | MHASSAN1 | Approved |