Permit: T18CM02307
Permit Details
Apply Date:
03/28/2018
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LEN5580 T17-M0020
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM02307
Permit Status: Final
Permit Description: SFR LEN5580 T17-M0020
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/28/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/28/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02307
Permit Status: Final
Permit Description: SFR LEN5580 T17-M0020
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM02307
Permit Description: SFR LEN5580 T17-M0020
Total Completed Inspections - 32
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2018 | PLUMBING - SEWER HCS CONNECT | RBALDWIN | Approved | |
| 05/14/2018 | PLUMBING - YARD WTR LINE/TEST | RBALDWIN | Approved | |
| 05/14/2018 | PLUMBING - ROUGH, SOIL | RBALDWIN | Approved | |
| 05/31/2018 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
| 05/31/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
| 05/31/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 07/18/2018 | EXT METAL CLIPS/EXT SHEATHING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/26/2018 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 07/31/2018 | ELECTRIC - CONSTRUCTION POWER | RCAMACH1 | Approved | IVRS - Inspection :* |
| 07/31/2018 | ELECTRIC - CABLE DROP | RCAMACH1 | Approved | IVRS - Inspection :* |
| 08/01/2018 | TEP CLEARANCE - AM | RCAMACHO | Approved | ECO |
| 08/14/2018 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | |
| 08/14/2018 | FIRE SPKLR - UG PIPING FLUSH | jvincent | Approved | |
| 08/14/2018 | FIRE SPKLR - UG, PIPING, HYDRO | jvincent | Approved | |
| 09/05/2018 | MECHANICAL - FINAL | BJONES | Approved | |
| 09/05/2018 | PLUMBING - FINAL | BJONES | Approved | |
| 09/05/2018 | ELECTRIC - FINAL | BJONES | Approved | |
| 09/05/2018 | BUILDING - FINAL | BJONES | Approved | |
| 09/12/2018 | MECHANICAL - INTERMEDIATE | BJONES | Approved | |
| 09/12/2018 | PLUMBING - INTERMEDIATE | BJONES | Approved | |
| 09/12/2018 | ELECTRIC - UFER | BJONES | Approved | |
| 09/12/2018 | U VALUE FOR WINDOW | BJONES | Approved | |
| 09/12/2018 | FRAMING | BJONES | Approved | |
| 09/12/2018 | SHEET ROCK NAILING | RCAMACH1 | Approved | IVRS - Inspection :* |
| 11/13/2018 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | SWG. Called in at 12:24 PM. |
| 11/13/2018 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | |
| 11/13/2018 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 11/13/2018 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | AP by Bill Jones on 9/4/18. |
| 11/13/2018 | STUCCO MESH | RCHANDLER | Approved | |
| 11/14/2018 | GAS CLEARANCE | RCHANDLER | Approved | |
| 11/30/2018 | FIRE - FINAL | GSereno | Approved | |
| 12/12/2018 | FIRE SPKLR - FINAL | gsereno1 | Approved |