Permit: T18CM02171
Permit Details
Apply Date:
03/22/2018
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT90817 T17-M0036
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM02171
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/22/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/22/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02171
Permit Status: Final
Permit Description: SFR RICHT90817 T17-M0036
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/22/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM02171
Permit Description: SFR RICHT90817 T17-M0036
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/04/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
04/04/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
04/11/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
04/11/2018 | BUILDING PRE-SLAB | MHASSAN1 | Approved | |
04/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | ADD ONE #4 REBAR CONT. AT PATIO PER DETAIL 13 SD.1 |
04/26/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | |
04/27/2018 | ROOF NAILING | MHASSAN1 | Approved | |
04/27/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN1 | Approved | |
05/16/2018 | ELECTRIC - UFER | DQUINN | Approved | |
05/16/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
05/16/2018 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
05/16/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
05/16/2018 | U VALUE FOR WINDOW | DQUINN | Approved | |
05/16/2018 | STUCCO MESH | DQUINN | Approved | |
05/18/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
05/22/2018 | FRAMING | MHASSAN1 | Approved | |
05/23/2018 | ELECTRIC - CONSTRUCTION POWER | MHASSAN1 | Approved | |
05/23/2018 | ELECTRIC - CABLE DROP | MHASSAN1 | Approved | PUT ADDRESS LABEL ON PANEL BEFORE TEP ARRIVES. |
05/24/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
05/31/2018 | SHEET ROCK NAILING | MHASSAN1 | Approved | |
07/06/2018 | GAS CLEARANCE | MHASSAN1 | Approved | OK TO CLEAR GAS FOR NEW SERVICE, SENT EMAIL TO SW GAS |
07/06/2018 | GAS CLEARANCE | TVALENCIA | Approved | |
07/10/2018 | MECHANICAL - FINAL | MHASSAN1 | Approved | FINISH REPAIRING REFREGERANT LEAK |
07/10/2018 | PLUMBING - FINAL | MHASSAN1 | Approved | |
07/10/2018 | OUTDOOR LIGHTING FINAL | MHASSAN1 | Approved | |
07/10/2018 | ELECTRIC - FINAL | MHASSAN1 | Approved | ADD OUTLET ABOVE COUNTER N. SIDE OF KITCHEN. 2' MAX FROM EDGE OF COUNTER. |
07/10/2018 | BUILDING - FINAL | MHASSAN1 | Approved |