Permit: T18CM02157
Permit Details
Status:
L of c
Type:
COMMERCIAL ADDITION
Address:
9225 E TANQUE VERDE RD
Address NEW:
9225 E TANQUE VERDE RD
Apply Date:
03/22/2018
Applicant:
N/A
Description:
GARAGE
Architects:
- WILLIAMS, WILLIAM
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO*** APA ***
Permit Reviews
Permit Number - T18CM02157
Permit Status: L of c
Permit Description: GARAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/22/2018 | COMMERCIAL - NEW | 05/31/2018 | COMPLETED |
| 05/31/2018 | RESUBMITTAL | 07/09/2018 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM02157
Permit Description: GARAGE
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2018 | ELECTRIC - FINAL | BJONES | Approved | WALK THROUGH ALL ELECTRICAL PANELS IN STORE WITH ELECTRICIAN. |
| 07/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | IVRS - Inspection :* |
| 08/08/2018 | ROOF NAILING | DQUINN | Approved | |
| 08/15/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | |
| 08/15/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | REFILL ABS AND TEST FOR LEAKS, NOT FULL AT TIME OF INSPECTION |
| 08/15/2018 | ELECTRIC - ABOVE CEILING | MHASSAN1 | Approved | |
| 08/15/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
| 08/15/2018 | FRAMING | MHASSAN1 | Approved | SEAL PENETRATIONS THROUGH TOP LAYER OF FIRE BLOCKING. IT WOULD BE RECOMMENDED THAT STUCCO MESH IS COMPLETED BEFORE YOU COVER UP THE WALLS. |
| 09/06/2018 | ELECTRIC - OUTDOOR LIGHTING | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/06/2018 | ELECTRIC - PROGRESS | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/06/2018 | ELECTRIC - SERVICE UPGRADE | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/06/2018 | ELECTRIC - CONSTRUCTION POWER | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | TEP CLEARANCE - AM | DFLORES | Approved | ECO |
| 09/10/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 09/11/2018 | FIRE - FINAL | gsereno1 | Approved | Approved no need to go out 9/12. Contractor called in again |
| 09/11/2018 | MECHANICAL - FINAL | DFLORES | Approved | |
| 09/11/2018 | OUTDOOR LIGHTING FINAL | DFLORES | Approved | |
| 09/12/2018 | SITE - SEWER | GWest | Approved | |
| 09/12/2018 | PLUMBING - FINAL | GWest | Approved | |
| 09/12/2018 | PLUMBING - SEWER HCS CONNECT | GWest | Approved | |
| 09/12/2018 | PLUMBING - BACK WATER VALVE | GWest | Approved | |
| 09/12/2018 | PLUMBING - YARD WTR LINE/TEST | GWest | Approved | |
| 09/12/2018 | PLUMBING - ROUGH, SOIL | GWest | Approved | |
| 09/12/2018 | ELECTRIC - TEMPORARY SERVICE | GWest | Approved | |
| 09/12/2018 | ELECTRIC - UFER | GWest | Approved | |
| 09/12/2018 | ELECTRIC - UNDERGROUND | GWest | Approved | |
| 09/12/2018 | BUILDING - FINAL | GWest | Approved | |
| 09/12/2018 | BUILDING - PROGRESS | GWest | Approved | |
| 09/12/2018 | STUCCO MESH | GWest | Approved | |
| 09/12/2018 | BUILDING PRE-SLAB | GWest | Approved |