Permit: T18CM02132
Permit Details
Apply Date:
03/21/2018
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT721 T16-M0077
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM02132
Permit Status: Final
Permit Description: SFR RICHT721 T16-M0077
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/21/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/21/2018 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T18CM02132
Permit Description: SFR RICHT721 T16-M0077
Total Completed Inspections - 29
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/30/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN1 | Approved | |
03/30/2018 | PLUMBING - ROUGH, SOIL | MHASSAN1 | Approved | |
04/04/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | |
04/04/2018 | BUILDING PRE-SLAB | MHASSAN1 | Approved | |
04/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | |
04/17/2018 | ROOF NAILING | MHASSAN1 | Approved | |
04/17/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN1 | Approved | |
04/30/2018 | MECHANICAL - INTERMEDIATE | MHASSAN1 | Approved | |
04/30/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN1 | Approved | |
04/30/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN1 | Approved | |
04/30/2018 | PLUMBING - INTERMEDIATE | MHASSAN1 | Approved | |
04/30/2018 | ELECTRIC - INTERMEDIATE | MHASSAN1 | Approved | |
04/30/2018 | U VALUE FOR WINDOW | MHASSAN1 | Approved | |
05/02/2018 | STUCCO MESH | MHASSAN1 | Approved | |
05/02/2018 | FRAMING | MHASSAN1 | Approved | |
05/02/2018 | ELECTRIC - CONSTRUCTION POWER | MHASSAN1 | Approved | |
05/02/2018 | ELECTRIC - CABLE DROP | MHASSAN1 | Approved | |
05/02/2018 | ELECTRIC - UFER | MHASSAN1 | Approved | |
05/02/2018 | STUCCO MESH | MHASSAN1 | Approved | CORRECTIONS NOT FIXED |
05/02/2018 | FRAMING | MHASSAN1 | Approved | SOME OF THE CORRECTIONS STILL NOT FIXED |
05/03/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
05/09/2018 | SHEET ROCK NAILING | MHASSAN1 | Approved | |
06/11/2018 | MECHANICAL - FINAL | MHASSAN1 | Approved | |
06/11/2018 | PLUMBING - PROGRESS | MHASSAN1 | Approved | OK TO CLEAR GAS FOR NEW SERVICE. SENT EMAIL IN TO SW GAS |
06/11/2018 | OUTDOOR LIGHTING FINAL | MHASSAN1 | Approved | |
06/12/2018 | GAS CLEARANCE | MHASSAN | Approved | |
06/15/2018 | PLUMBING - FINAL | MHASSAN1 | Approved | |
06/15/2018 | ELECTRIC - FINAL | MHASSAN1 | Approved | STRAP FLEX TO CONDENSER TO WALL |
06/15/2018 | BUILDING - FINAL | MHASSAN1 | Approved |